[Code of Federal Regulations]
[Title 32, Volume 4]
[Revised as of July 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 32CFR651.42]

[Page 415]
 
                       TITLE 32--NATIONAL DEFENSE
 
              CHAPTER V--DEPARTMENT OF THE ARMY (CONTINUED)
 
PART 651--ENVIRONMENTAL ANALYSIS OF ARMY ACTIONS (AR 200-2)--Table of Contents
 
                Subpart F--Environmental Impact Statement
 
Sec. 651.42  Actions normally requiring an EIS.

    The following actions normally require an EIS:
    (a) Significant expansion of a military facility or installation.
    (b) Construction of facilities that have a significant effect on 
wetlands, coastal zones, or other areas of critical environmental 
concern.
    (c) The disposal of nuclear materials, munitions, explosives, 
industrial and military chemicals, and other hazardous or toxic 
substances that have the potential to cause significant environmental 
impact.
    (d) Land acquisition, leasing, or other actions that may lead to 
significant changes in land use.
    (e) Realignment or stationing of a brigade or larger table of 
organization equipment (TOE) unit during peacetime (except where the 
only significant impacts are socioeconomic, with no significant 
biophysical environmental impact).
    (f) Training exercises conducted outside the boundaries of an 
existing military reservation where significant environmental damage 
might occur.
    (g) Major changes in the mission or facilities either affecting 
environmentally sensitive resources (see Sec. 651.29(c)) or causing 
significant environmental impact (see Sec. 651.39).