[Code of Federal Regulations]
[Title 34, Volume 1]
[Revised as of July 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 34CFR75.219]

[Page 136]
 
                           TITLE 34--EDUCATION
 
PART 75--DIRECT GRANT PROGRAMS--Table of Contents
 
                     Subpart D--How Grants Are Made
 
Sec.  75.219  Exceptions to the procedures under Sec.  75.217.

    The Secretary may select an application for funding without 
following the procedures in Sec.  75.217 if:
    (a) The objectives of the project cannot be achieved unless the 
Secretary makes the grant before the date grants can be made under the 
procedures in Sec.  75.217;
    (b)(1) The application was evaluated under the preceding competition 
of the program;
    (2) The application rated high enough to deserve selection under 
Sec.  75.217; and
    (3) The application was not selected for funding because the 
application was mishandled by the Department; or
    (c) The Secretary receives an unsolicited application that meets the 
requirements of Sec.  75.222.

(Authority: 20 U.S.C. 1221e-3 and 3474)

[45 FR 22497, Apr. 3, 1980. Redesignated at 45 FR 77368, Nov. 21, 1980, 
as amended at 52 FR 27804, July 24, 1987; 60 FR 12096, Mar. 3, 1995]