Sec. 219.9  Revision.

    (a) Application of the revision process. Revision of a plan is 
required by 16 U.S.C. 1604(f)(5). The revision process is a review of 
the overall management of a unit of the National Forest System and an 
opportunity to consider the likely results if plan decisions were to 
remain in effect.
    (b) Initiating revision. To begin the revision process, the 
responsible official must:
    (1) Provide opportunities for collaboration consistent with 
Sec. 219.12 through Sec. 219.18;
    (2) Summarize those issues the responsible official determines to be 
appropriate for consideration (Sec. 219.4), any relevant inventories, 
new data, findings and conclusions from appropriate broad-scale 
assessments and local analyses, monitoring and evaluation results, new 
or revised Forest Service policies, relevant portions of the Forest 
Service national strategic plan, and changes in circumstances affecting 
the entire or significant portions of the plan area;
    (3) Develop the information and complete the analyses described in 
Sec. 219.20(a) and Sec. 219.21(a);

[[Page 42]]

    (4) Evaluate the effectiveness of the current plan in contributing 
to sustainability (Secs. 219.19-219.21) based on the information, 
analyses, and requirements described in Sec. 219.20(a) and (b) and 
Sec. 219.21(a) and (b), and provide for an independent scientific peer 
review (Sec. 219.22) of the evaluation;
    (5) Identify new proposals for special areas, special designation, 
or for recommendation as wilderness (Sec. 219.27);
    (6) Identify specific watersheds in need of protective or 
restoration measures;
    (7) Identify lands classified as not suitable for timber production 
(Sec. 219.28);
    (8) Identify and evaluate inventoried roadless areas and unroaded 
areas based on the information, analyses, and requirements in 
Sec. 219.20(a) and Sec. 219.21(a). During the plan revision process or 
at other times as deemed appropriate, the responsible official must 
determine which inventoried roadless areas and unroaded areas warrant 
additional protection and the level of protection to be afforded; and
    (9) Develop an estimate of outcomes that would be anticipated, 
including uses, values, products, or services, for a 15-year period 
following initiation of the revision process, if the plan decisions in 
effect at the time the revision process began remain in effect.
    (c) Public notice of revision process and review of information. 
After the responsible official has compiled the information required 
under paragraph (b) of this section, the responsible official must give 
public notice of the plan revision process and make the information 
compiled under paragraph (b) of this section available for public 
comment for at least 45 calendar days.
    (d) Notice of Intent. Based upon the information compiled under 
paragraph (b) of this section and any comments received during the 
comment period required under paragraph (c) of this section, the 
responsible official must publish a Notice of Intent to prepare an 
environmental impact statement to add, modify, remove, or continue in 
effect the decisions embodied in a plan. The responsible official must 
give the public notice and an opportunity to comment on the draft 
environmental impact statement for at least 90 calendar days. Following 
public comment, the responsible official must oversee preparation of a 
final environmental impact statement in accordance with Forest Service 
NEPA procedures.
    (e) Final decision on plan revision. The revision process is 
completed when the responsible official signs a record of decision for a 
plan revision.