Sec. 60-4.6  Goals and timetables.

    The Director, from time to time, shall issue goals and timetables 
for minority and female utilization which shall be based on appropriate 
workforce, demographic or other relevant data and which shall cover 
construction projects or construction contracts performed in specific 
geographical areas. The goals, which shall be applicable to each 
construction trade in a covered contractor's or subcontractor's entire 
workforce which is working in the area covered by the goals and 
timetables, shall be published as notices in the Federal Register, and 
shall be inserted by the contracting officers and applicants, as 
applicable, in

[[Page 152]]

the Notice required by 41 CFR 60-4.2. Covered construction contractors 
performing construction work in geographical areas where they do not 
have a Federal or federally assisted construction contract shall apply 
the minority and female goals established for the geographical area 
where the work is being performed.

[45 FR 65978, Oct. 3, 1980]