Sec. 51c.504  Project elements.

    (a) General requirements. A grantee which has received a grant under 
section 330 of the Act for a project which includes the acquisition and/
or modernization of an existing building must:
    (1) Assurances. Comply with the assurances provided pursuant to this 
subpart.
    (2) Approval of estimated cost. Not enter into any contract for the 
acquisition and/or modernization funded under this subpart where the 
cost of such acquisition and/or modernization exceeds the estimates in 
the application, without the prior approval of the Secretary.
    (3) Non-default. Make every effort to prevent any default on any 
loan secured by the building and, in the event of a default, promptly 
notify the Secretary of the default and make every effort on a timely 
basis to cure the default.
    (b) Requirements for acquisition grants. In addition to the 
requirements of paragraph (a) of this section, a grantee which has 
received a grant under section 330 of the Act for a project which 
includes the acquisition of an existing building must:
    (1) Bona-fide sale. Acquire or, in the case of a grant solely for 
amortization of principal and payment of interest on an existing loan, 
have acquired the existing building pursuant to a bona-fide sale 
involving an actual cost to the applicant and resulting in additional or 
improved facilities for the purposes of the project.
    (2) Standards of construction and equipment. Except in the case of a 
grant solely for amortization of principal and payment of interest on an 
existing loan, obtain a determination by the Secretary that the facility 
conforms (or upon completion of any necessary alteration and renovation 
or modernization will conform) to the standards set forth in 
Sec. 51c.503(a)(7)(iii) of this subpart before entering into a final or 
unconditional contract for the acquisition. Where the Secretary finds 
that exceptions to or modifications of any such standards would be 
consistent with the purposes of the Act and of the program, he may 
authorize such exceptions or modifications.
    (3) Financing. Where the grantee will obtain a loan secured by the 
building in order to acquire the building, obtain such financing at the 
lowest current rate prevailing in the area for comparable loans on 
comparable facilities.
    (c) Requirements for modernization grants. In addition to the 
requirements of paragraph (a) of this section, a grantee which has 
received a grant under section 330 of the Act for a project which 
includes the modernization of an existing building must:
    (1) Costs in excess of approved costs. Finance all costs in excess 
of the estimated costs approved in the application and submit to the 
Secretary for

[[Page 191]]

prior approval any changes that substantially alter the scope of the 
function, utilities, or safety of the facility.
    (2) Competitive bids. (i) Obtain the approval of the Secretary 
before the project is advertised or placed on the market for bidding; 
such approval must include a determination by the Secretary that the 
final plans and specifications conform to the standards set forth in 
Sec. 51c.503(a)(7)(iii) of these regulations.
    (ii) Except as otherwise provided by State or local law, contract 
for construction (including the purchase and installation of built-in 
equipment) on a lump sum fixed-price basis, and award contracts on the 
basis of competitive bidding obtained by public advertising with award 
of the contracts to the lowest responsive and responsible bidders. The 
provision for exceptions based on State and local law shall not be 
invoked to give local contractors or suppliers a percentage preference 
over non-local contractors bidding for the same contract. Such practices 
are precluded by this paragraph.
    (3) Construction contracts. (i) Include the following conditions and 
provisions in all construction contracts for the modernization project:
    (A) The provisions set forth in ``DHHS Requirements for Federally 
Assisted Construction Contracts Regarding Labor Standards and Equal 
Employment Opportunities,'' Form DHHS 514 (rev. 7/76) (issued by the 
Office of Grants Administration Policy, U.S. Department of Health and 
Human Services) pertaining to the Davis-Bacon Act, the Contract Work 
Hours Standards Act, and the Copeland Act (Anti-Kickback) Regulations, 
except in the case of contracts in the amount of $2,000 or less; and 
pertaining to Executive Order 11246, 30 FR 12319 (September 24, 1965), 
as amended, relating to nondiscrimination in construction contract 
employment, except in the case of contracts in the amount of $10,000 or 
less;
    (B) That the contractor shall furnish performance and payment bonds 
each of which shall be in the full amount of the contract price, and 
shall maintain, during the life of the contract, adequate fire, 
workmen's compensation, public liability, and property damage insurance: 
Provided, however, That in the case of a State or local unit of 
government which enters into a construction contract of less than 
$100,000, State or local provisions with respect to performance and 
payment bonds shall be deemed to meet the requirements of this 
paragraph; and
    (C) That the Secretary shall have access at all reasonable times to 
work wherever it is in preparation or progress, and the contractor shall 
provide proper facilities for such access and inspection.
    (ii) Executive Order 11246. Comply with the applicable requirements 
of Executive Order 11246, 30 FR 12319 (September 24, 1965) as amended, 
relating to nondiscrimination in construction contract employment, and 
the applicable rules, regulations, and procedures prescribed pursuant 
thereto.
    (4) Modernization supervision. Provide and maintain competent and 
adequate architectural or engineering supervision and inspection at the 
modernization site to insure that the completed work conforms with the 
plans and specifications.
    (5) Completion responsibility. Complete the modernization in 
accordance with the grant application and the approved plans and 
specifications.
    (6) Progress reports. Furnish progress reports and such other 
information concerning the modernization as the Secretary may require.
    (d) The Secretary may at any time approve exceptions to the 
provisions of this section where he finds that such exceptions are not 
inconsistent with section 330 of the Act, other requirements of law, or 
the purposes of the program.

[41 FR 57000, Dec. 30, 1976, as amended at 43 FR 5352, Feb. 7, 1978]