Sec. 12.63  Period of availability of funds.

    (a) General. Where a funding period is specified, a grantee may 
charge to the award only costs resulting from obligations of the funding 
period unless carryover of unobligated balances is permitted, in which 
case the carryover balances may be charged for costs resulting from 
obligations of the subsequent funding period.
    (b) Liquidation of obligations. A grantee must liquidate all 
obligations incurred under the award not later than 90 days after the 
end of the funding period (or as specified in a program regulation) to 
coincide with the submission of the annual Financial Status Report (SF-
269). The Federal agency may extend this deadline at the request of the 
grantee.