[Code of Federal Regulations]
[Title 45, Volume 4]
[Revised as of October 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 45CFR1336.31]

[Page 281]
 
                        TITLE 45--PUBLIC WELFARE
 
CHAPTER XIII--OFFICE OF HUMAN DEVELOPMENT SERVICES, DEPARTMENT OF HEALTH 
                           AND HUMAN SERVICES
 
PART 1336--NATIVE AMERICAN PROGRAMS--Table of Contents
 
                   Subpart C--Native American Projects
 
Sec. 1336.31  Project approval procedures.

    (a) Each applicant for financial assistance under section 803 of the 
Act must submit a work plan that falls within the statutory requirements 
of the Act and meets the criteria of program announcements published by 
ANA in the Federal Register. If the proposed project extends beyond one 
year, a work plan must be submitted for the period of time specified by 
the Commissioner in the Program Announcement. ANA will determine whether 
to approve all, part, or none of the requested work plan. Proposed 
changes to the approved work plan must receive the written approval of 
ANA prior to implementation by the recipient.
    (b) ANA will negotiate the approved project goals, objectives, work 
plan, and the funding level for each budget period with each recipient.
    (c) The evaluation for the purpose of making an approval decision on 
each proposed work plan will take into account the proposal's 
conformance with ANA program purposes and the recipient's past 
performance and accomplishments.
    (d) Financial assistance awarded under section 803 may be renewed by 
ANA to grantees based on acceptable work plans and past performance.

(Approved by the Office of Management and Budget under control number 
0980-0016)