[Code of Federal Regulations]
[Title 48, Volume 6]
[Revised as of October 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR1733.209]

[Page 173]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
               CHAPTER 17--OFFICE OF PERSONNEL MANAGEMENT
 
PART 1733--PROTESTS, DISPUTES, AND APPEALS--Table of Contents
 
                  Subpart 1733.2--Disputes and Appeals
 
Sec. 1733.209  Suspected fraudulent claims.

    If the contractor is unable to support any part of the claim and 
there is evidence that the inability is attributable to 
misrepresentation of fact or to fraud on the part of the contractor, the 
contracting officer shall refer the matter through the head of the 
contracting activity to OPM's Offices of the Inspector General and the 
General Counsel.