Sec. 193.2017  Plans and procedures.

    (a) Each operator shall maintain at each LNG plant the plans and 
procedures required for that plant by this part. The plans and 
procedures must be available upon request for review and inspection by 
the Administrator or any State Agency that has submitted a current 
certification or agreement with respect to the plant under the pipeline 
safety laws (49 U.S.C. 60101 et seq.). In addition, each change to the 
plans or procedures must be available at the LNG plant for review and 
inspection within 20 days after the change is made.
    (b) The Administrator or the State Agency that has submitted a 
current certification under section 5(a) of the Natural Gas Pipeline 
Safety Act with respect to the pipeline facility governed by an 
operator's plans and procedures may, after notice and opportunity for 
hearing as provided in 49 CFR 190.237 or the relevant State procedures, 
require the operator to amend its plans and procedures as necessary to 
provide a reasonable level of safety.

[Amdt. 193-2, 45 FR 70404, Oct. 23, 1980, as amended by Amdt. 193-7, 56 
FR 31090, July 9, 1991; Amdt. 193-10, 61 FR 18517, Apr. 26, 1996]