[Code of Federal Regulations]
[Title 49, Volume 4]
[Revised as of October 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 49CFR213.57]

[Page 97-99]
 
                        TITLE 49--TRANSPORTATION
 
       CHAPTER II--FEDERAL RAILROAD ADMINISTRATION, DEPARTMENT OF 
                             TRANSPORTATION
 
PART 213--TRACK SAFETY STANDARDS--Table of Contents
 
                        Subpart C--Track Geometry
 
Sec. 213.57  Curves; elevation and speed limitations.

    (a) The maximum crosslevel on the outside rail of a curve may not be 
more than 8 inches on track Classes 1 and 2 and 7 inches on Classes 3 
through 5. Except as provided in Sec. 213.63, the outside rail of a 
curve may not be lower than the inside rail. (The first sentence of 
paragraph (a) is applicable September 21, 1999.)
    (b)(1) The maximum allowable operating speed for each curve is 
determined by the following formula--
[GRAPHIC] [TIFF OMITTED] TR22JN98.001

Where--

Vmax = Maximum allowable operating speed (miles per hour).
Ea = Actual elevation of the outside rail (inches).\1\
---------------------------------------------------------------------------

    \1\ Actual elevation for each 155 foot track segment in the body of 
the curve is determined by averaging the elevation for 10 points through 
the segment at 15.5 foot spacing. If the curve length is less than 155 
feet, average the points through the full length of the body of the 
curve.
---------------------------------------------------------------------------

D = Degree of curvature (degrees).\2\
---------------------------------------------------------------------------

    \2\ Degree of curvature is determined by averaging the degree of 
curvature over the same track segment as the elevation.

    (2) Table 1 of Appendix A is a table of maximum allowable operating 
speed computed in accordance with this formula for various elevations 
and degrees of curvature.
    (c)(1) For rolling stock meeting the requirements specified in 
paragraph (d) of this section, the maximum operating speed for each 
curve may be determined by the following formula--
[GRAPHIC] [TIFF OMITTED] TR22JN98.002

Where--

Vmax = Maximum allowable operating speed (miles per hour).
Ea = Actual elevation of the outside rail (inches).\1\
D = Degree of curvature (degrees).\2\

    (2) Table 2 of Appendix A is a table of maximum allowable operating 
speed

[[Page 98]]

computed in accordance with this formula for various elevations and 
degrees of curvature.
    (d) Qualified equipment may be operated at curving speeds determined 
by the formula in paragraph (c) of this section, provided each specific 
class of equipment is approved for operation by the Federal Railroad 
Administration and the railroad demonstrates that:
    (1) When positioned on a track with a uniform 4-inch superelevation, 
the roll angle between the floor of the equipment and the horizontal 
does not exceed 5.7 degrees; and
    (2) When positioned on a track with a uniform 6 inch superelevation, 
no wheel of the equipment unloads to a value of 60 percent of its static 
value on perfectly level track, and the roll angle between the floor of 
the equipment and the horizontal does not exceed 8.6 degrees.
    (3) The track owner shall notify the Federal Railroad Administrator 
no less than 30 calendar days prior to the proposed implementation of 
the higher curving speeds allowed under the formula in paragraph (c) of 
this section. The notification shall be in writing and shall contain, at 
a minimum, the following information--
    (i) A complete description of the class of equipment involved, 
including schematic diagrams of the suspension systems and the location 
of the center of gravity above top of rail;
    (ii) A complete description of the test procedure \3\ and 
instrumentation used to qualify the equipment and the maximum values for 
wheel unloading and roll angles which were observed during testing;
---------------------------------------------------------------------------

    \3\ The test procedure may be conducted in a test facility whereby 
all the wheels on one side (right or left) of the equipment are 
alternately raised and lowered by 4 and 6 inches and the vertical wheel 
loads under each wheel are measured and a level is used to record the 
angle through which the floor of the equipment has been rotated.
---------------------------------------------------------------------------

    (iii) Procedures or standards in effect which relate to the 
maintenance of the suspension system for the particular class of 
equipment; and
    (iv) Identification of line segment on which the higher curving 
speeds are proposed to be implemented.
    (e) A track owner, or an operator of a passenger or commuter 
service, who provides passenger or commuter service over trackage of 
more than one track owner with the same class of equipment may provide 
written notification to the Federal Railroad Administrator with the 
written consent of the other affected track owners.
    (f) Equipment presently operating at curving speeds allowed under 
the formula in paragraph (c) of this section, by reason of conditional 
waivers granted by the Federal Railroad Administration, shall be 
considered to have successfully complied with the requirements of 
paragraph (d) of this section.
    (g) A track owner or a railroad operating above Class 5 speeds, may 
request approval from the Federal Railroad Administrator to operate 
specified equipment at a level of cant deficiency greater than four 
inches in accordance with Sec. 213.329(c) and (d) on curves in Class 1 
through 5 track which are contiguous to the high speed track provided 
that--
    (1) The track owner or railroad submits a test plan to the Federal 
Railroad Administrator for approval no less than thirty calendar days 
prior to any proposed implementation of the higher curving speeds. The 
test plan shall include an analysis and determination of carbody 
acceleration safety limits for each vehicle type which indicate wheel 
unloading of 60 percent in a steady state condition and 80 percent in a 
transient (point by point) condition. Accelerometers shall be laterally-
oriented and floor-mounted near the end of a representative vehicle of 
each type;
    (2) Upon FRA approval of a test plan, the track owner or railroad 
conducts incrementally increasing train speed test runs over the curves 
in the identified track segment(s) to demonstrate that wheel unloading 
is within the limits prescribed in paragraph (g)(1) of this section;
    (3) Upon FRA approval of a cant deficiency level, the track owner or 
railroad inspects the curves in the identified track segment with a 
Track Geometry Measurement System (TGMS) qualified in accordance with 
Sec. 213.333 (b) through (g) at an inspection frequency of at least 
twice annually with not less

[[Page 99]]

than 120 days interval between inspections; and
    (4) The track owner or railroad operates an instrumented car having 
dynamic response characteristics that are representative of other 
equipment assigned to service or a portable device that monitors on-
board instrumentation on trains over the curves in the identified track 
segment at the revenue speed profile at a frequency of at least once 
every 90-day period with not less than 30 days interval between 
inspections. The instrumented car or the portable device shall monitor a 
laterally-oriented accelerometer placed near the end of the vehicle at 
the floor level. If the carbody lateral acceleration measurement exceeds 
the safety limits prescribed in paragraph (g)(1), the railroad shall 
operate trains at curving speeds in accordance with paragraph (b) or (c) 
of this section; and
    (5) The track owner or railroad shall maintain a copy of the most 
recent exception printouts for the inspections required under paragraphs 
(g)(3) and (4) of this section.

[63 FR 34029, June 22, 1998; 63 FR 54078, Oct. 8, 1998]