[Code of Federal Regulations] [Title 49, Volume 1] [Revised as of October 1, 2002] From the U.S. Government Printing Office via GPO Access [CITE: 49CFR26.29] [Page 272] TITLE 49--TRANSPORTATION SUBTITLE A--OFFICE OF THE SECRETARY OF TRANSPORTATION PART 26--PARTICIPATION BY DISADVANTAGED BUSINESS ENTERPRISES IN DEPARTMENT OF TRANSPORTATION FINANCIAL ASSISTANCE PROGRAMS--Table of Contents Subpart B--Administrative Requirements for DBE Programs for Federally- Assisted Contracting Sec. 26.29 What prompt payment mechanisms must recipients have? (a) You must establish, as part of your DBE program, a contract clause to require prime contractors to pay subcontractors for satisfactory performance of their contracts no later than a specific number of days from receipt of each payment you make to the prime contractor. This clause must also require the prompt return of retainage payments from the prime contractor to the subcontractor within a specific number of days after the subcontractor's work is satisfactorily completed. (1) This clause may provide for appropriate penalties for failure to comply, the terms and conditions of which you set. (2) This clause may also provide that any delay or postponement of payment among the parties may take place only for good cause, with your prior written approval. (b) You may also establish, as part of your DBE program, any of the following additional mechanisms to ensure prompt payment: (1) A contract clause that requires prime contractors to include in their subcontracts language providing that prime contractors and subcontractors will use appropriate alternative dispute resolution mechanisms to resolve payment disputes. You may specify the nature of such mechanisms. (2) A contract clause providing that the prime contractor will not be reimbursed for work performed by subcontractors unless and until the prime contractor ensures that the subcontractors are promptly paid for the work they have performed. (3) Other mechanisms, consistent with this part and applicable state and local law, to ensure that DBEs and other contractors are fully and promptly paid. [[Page 273]]