[Code of Federal Regulations]
[Title 49, Volume 1]
[Revised as of October 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 49CFR26.53]

[Page 279-280]
 
                        TITLE 49--TRANSPORTATION
 
          SUBTITLE A--OFFICE OF THE SECRETARY OF TRANSPORTATION
 
PART 26--PARTICIPATION BY DISADVANTAGED BUSINESS ENTERPRISES IN DEPARTMENT OF TRANSPORTATION FINANCIAL ASSISTANCE PROGRAMS--Table of Contents
 
           Subpart C--Goals, Good Faith Efforts, and Counting
 
Sec. 26.53  What are the good faith efforts procedures recipients follow in situations where there are contract goals?

    (a) When you have established a DBE contract goal, you must award 
the contract only to a bidder/offeror who makes good faith efforts to 
meet it. You must determine that a bidder/offeror has made good faith 
efforts if the bidder/offeror does either of the following things:
    (1) Documents that it has obtained enough DBE participation to meet 
the goal; or
    (2) Documents that it made adequate good faith efforts to meet the 
goal, even though it did not succeed in obtaining enough DBE 
participation to do so. If the bidder/offeror does document adequate 
good faith efforts, you must not deny award of the contract on the basis 
that the bidder/offeror failed to meet the goal. See Appendix A of this 
part for guidance in determining the adequacy of a bidder/offeror's good 
faith efforts.
    (b) In your solicitations for DOT-assisted contracts for which a 
contract goal has been established, you must require the following:
    (1) Award of the contract will be conditioned on meeting the 
requirements of this section;
    (2) All bidders/offerors will be required to submit the following 
information to the recipient, at the time provided in paragraph (b)(3) 
of this section:
    (i) The names and addresses of DBE firms that will participate in 
the contract;
    (ii) A description of the work that each DBE will perform;
    (iii) The dollar amount of the participation of each DBE firm 
participating;
    (iv) Written documentation of the bidder/offeror's commitment to use 
a DBE subcontractor whose participation it submits to meet a contract 
goal;
    (v) Written confirmation from the DBE that it is participating in 
the contract as provided in the prime contractor's commitment; and
    (vi) If the contract goal is not met, evidence of good faith efforts 
(see Appendix A of this part); and
    (3) At your discretion, the bidder/offeror must present the 
information required by paragraph (b)(2) of this section--
    (i) Under sealed bid procedures, as a matter of responsiveness, or 
with initial proposals, under contract negotiation procedures; or

[[Page 280]]

    (ii) At any time before you commit yourself to the performance of 
the contract by the bidder/offeror, as a matter of responsibility.
    (c) You must make sure all information is complete and accurate and 
adequately documents the bidder/offeror's good faith efforts before 
committing yourself to the performance of the contract by the bidder/
offeror.
    (d) If you determine that the apparent successful bidder/offeror has 
failed to meet the requirements of paragraph (a) of this section, you 
must, before awarding the contract, provide the bidder/offeror an 
opportunity for administrative reconsideration.
    (1) As part of this reconsideration, the bidder/offeror must have 
the opportunity to provide written documentation or argument concerning 
the issue of whether it met the goal or made adequate good faith efforts 
to do so.
    (2) Your decision on reconsideration must be made by an official who 
did not take part in the original determination that the bidder/offeror 
failed to meet the goal or make adequate good faith efforts to do so.
    (3) The bidder/offeror must have the opportunity to meet in person 
with your reconsideration official to discuss the issue of whether it 
met the goal or made adequate good faith efforts to do so.
    (4) You must send the bidder/offeror a written decision on 
reconsideration, explaining the basis for finding that the bidder did or 
did not meet the goal or make adequate good faith efforts to do so.
    (5) The result of the reconsideration process is not 
administratively appealable to the Department of Transportation.
    (e) In a ``design-build'' or ``turnkey'' contracting situation, in 
which the recipient lets a master contract to a contractor, who in turn 
lets subsequent subcontracts for the work of the project, a recipient 
may establish a goal for the project. The master contractor then 
establishes contract goals, as appropriate, for the subcontracts it 
lets. Recipients must maintain oversight of the master contractor's 
activities to ensure that they are conducted consistent with the 
requirements of this part.
    (f)(1) You must require that a prime contractor not terminate for 
convenience a DBE subcontractor listed in response to paragraph (b)(2) 
of this section (or an approved substitute DBE firm) and then perform 
the work of the terminated subcontract with its own forces or those of 
an affiliate, without your prior written consent.
    (2) When a DBE subcontractor is terminated, or fails to complete its 
work on the contract for any reason, you must require the prime 
contractor to make good faith efforts to find another DBE subcontractor 
to substitute for the original DBE. These good faith efforts shall be 
directed at finding another DBE to perform at least the same amount of 
work under the contract as the DBE that was terminated, to the extent 
needed to meet the contract goal you established for the procurement.
    (3) You must include in each prime contract a provision for 
appropriate administrative remedies that you will invoke if the prime 
contractor fails to comply with the requirements of this section.
    (g) You must apply the requirements of this section to DBE bidders/
offerors for prime contracts. In determining whether a DBE bidder/
offeror for a prime contract has met a contract goal, you count the work 
the DBE has committed to performing with its own forces as well as the 
work that it has committed to be performed by DBE subcontractors and DBE 
suppliers.