Sec. 2301.24  Final Federal payment.

    If the total allowable, allocable, and reasonable costs incurred in 
completing the planning or construction project are less than the total 
project award amount, the Agency shall reduce the amount of the final 
Federal share on a pro rata basis. If, however, the actual costs 
incurred in completing the project are more than the estimated total 
project costs, in no case will the final Federal funds paid exceed the 
grant award.