Sec. 622.32  Reviews and approvals.

    (a) The watershed plan-environmental impact statement (or 
assessment) will be subject to internal technical reviews, sponsor and 
other local party review, interagency review by other Federal, state, 
and concerned groups, and a final review as stated in NRCS's National 
Watersheds Manual.
    (b) After thorough review by NRCS and other agencies, the NRCS and 
the sponsors shall accept the plan-EIS or plan-EA by signing the 
watershed agreement. The watershed plan must be approved by the 
Committees of Congress or the Chief of NRCS. Funding for installation 
can then be granted by the Chief of NRCS.