Sec. 1493.310  Payment for loss.

    (a) Determination of CCC's liability. Upon receipt in good order of 
the information and documents required under Sec. 1493.300, CCC will 
determine whether or not a loss has occurred for which CCC is liable 
under the facility payment guarantee, this subpart, program 
announcement(s) and notice(s) to participants. If CCC determines that it 
is liable to the exporter or the exporter's assignee, CCC will pay the 
exporter or the exporter's assignee in accordance with paragraphs (b) 
and (c) of this section.
    (b) Amount of CCC's liability. CCC's maximum liability for any 
claims for loss submitted with respect to any facility payment 
guarantee, not including any late interest payments due in accordance 
with paragraph (c) of this section, will be limited to the lesser of:
    (1) The guaranteed value as stated in the facility payment 
guarantee, plus eligible interest; or
    (2) The guaranteed percentage (as indicated in the facility payment 
guarantee) of the exported value indicated in the evidence of export 
report (Sec. 1493.280(a)(7)), plus eligible interest.
    (c) Late interest payment. If a claim is not paid within one day of 
receipt of a claim which CCC has determined to be in good order, late 
interest will accrue in favor of the exporter or the exporter's assignee 
beginning with the first day after the claim was found by CCC to be in 
good order and continuing until and including the date that payment is 
made by CCC. Late interest will be paid on the guaranteed amount,

[[Page 833]]

as determined by paragraphs (b)(1) and (2) of this section, and will be 
calculated based on the latest average investment rate of the most 
recent Treasury 91-day bill auction as announced by the Department of 
Treasury as of the due date.
    (d) Accelerated payments. CCC will pay claims only for losses on 
amounts not paid as scheduled. CCC will not pay claims for amounts due 
under an accelerated payment clause in the export sales contract, the 
foreign bank's letter of credit, or any obligation owed by the foreign 
bank to the assignee U.S. financial institution which is related to the 
foreign bank's letter of credit issued in favor of the exporter, unless 
it is determined to be in the best interest of CCC by the Controller, 
CCC. Notwithstanding the foregoing, CCC at its option may declare the 
entire amount of the unpaid balance, plus accrued interest, in default 
and make payment to the exporter or the exporter's assignee in addition 
to such other claimed amount as may be due from CCC.
    (e) Action against the assignee. Notwithstanding any other provision 
in this subpart to the contrary, with regard to the value of goods or 
services covered by a facility payment guarantee, CCC will not hold the 
assignee responsible or take any action or raise any defense against the 
assignee for any action, omission or statement by the exporter of which 
the assignee has no knowledge, provided that:
    (1) The exporter complies with the reporting requirements under 
Sec. 1493.270 and Sec. 1493.280 excluding post-export adjustments (i.e., 
corrections of evidence of export reports); and
    (2) The exporter or the exporter's assignee furnishes the statements 
and documents specified in Sec. 1493.300.