                          TITLE 7--AGRICULTURE
 
    CHAPTER XVII--RURAL UTILITIES SERVICE, DEPARTMENT OF AGRICULTURE
 
PART 1710--GENERAL AND PRE-LOAN POLICIES AND PROCEDURES COMMON TO ELECTRIC LOANS AND GUARANTEES--Table of Contents
 
                        Subpart E--Load Forecasts
 
Sec. 1710.203  Requirement to prepare a load forecast--distribution borrowers.

    (a) A distribution borrower that is a member of a power supply 
borrower with a total utility plant of $500 million or more must 
maintain an approved load forecast that meets the requirements of this 
subpart on an ongoing basis and provide an approved load forecast in 
support of any request for RUS financial assistance. The distribution 
borrower may comply with this requirement by participation in and 
inclusion of its load forecasting information in the approved load 
forecast of its power supply borrower. The distribution borrower's load 
forecast must be prepared pursuant to the approved load forecast work 
plan of its power supply borrower.
    (b) A distribution borrower that is a member of a power supply 
borrower which is itself a member of another power supply borrower that 
has a total utility plant of $500 million or more must maintain an 
approved load forecast that meets the requirements of this subpart on an 
ongoing basis and provide an approved load forecast in support of any 
request for RUS financial assistance. The distribution borrower may 
comply with this requirement by participation in and inclusion of its 
load forecasting information in the approved load forecast of its power 
supply borrower. The distribution borrower's approved load forecast must 
be prepared pursuant to the approved load forecast work plan of the 
power supply borrower with total utility plant in excess of $500 
million.
    (c) A distribution borrower that is a member of a power supply 
borrower with a total utility plant of less than $500 million must 
provide an approved load forecast that meets the requirements of this 
subpart in support of an

[[Page 114]]

application for any RUS loan or loan guarantee that exceeds $3 million 
or 5 percent of total utility plant, whichever is greater. The 
distribution borrower may comply with this requirement by participation 
in and inclusion of its load forecasting information in the approved 
load forecast of its power supply borrower. The borrower is not required 
to maintain on an ongoing basis either an approved load forecast or an 
approved load forecast work plan.
    (d) A distribution borrower with a total utility plant of less than 
$500 million and that is unaffiliated with a power supply borrower must 
provide an approved load forecast that meets the requirements of this 
subpart in support of an application for any RUS loan or loan guarantee 
which exceeds $3 million or 5 percent of total utility plant, whichever 
is greater. The borrower is not required to maintain on an ongoing basis 
either an approved load forecast or an approved load forecast work plan.
    (e) A distribution borrower with a total utility plant of $500 
million or more must maintain an approved load forecast that meets the 
requirements of this subpart on an ongoing basis and provide an approved 
load forecast in support of any request for RUS financing assistance. 
The borrower must also maintain an approved load forecast work plan. The 
distribution borrower may comply with this requirement by participation 
in and inclusion of its load forecasting information in the approved 
load forecast of its power supply borrower.