[Code of Federal Regulations]
[Title 7, Volume 11]
[Revised as of January 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 7CFR1710.209]

[Page 117-118]
 
                          TITLE 7--AGRICULTURE
 
    CHAPTER XVII--RURAL UTILITIES SERVICE, DEPARTMENT OF AGRICULTURE
 
PART 1710--GENERAL AND PRE-LOAN POLICIES AND PROCEDURES COMMON TO ELECTRIC LOANS AND GUARANTEES--Table of Contents
 
                        Subpart E--Load Forecasts
 
Sec. 1710.209  Approval requirements for load forecast work plans.

    (a) In addition to the approved load forecast required under 
Secs. 1710.202 and 1710.203, any power supply borrower with a total 
utility plant of $500 million or more and any distribution borrower with 
a total utility plant of $500 million or more must maintain an approved 
load forecast work plan. RUS borrowers that are members of a power 
supply borrower with a total utility plant of $500 million or more must 
cooperate in the preparation of and submittal of the load forecast work 
plan of their power supply borrower.
    (b) An approved load forecast work plan establishes the process for 
the preparation and maintenance of a comprehensive database for the 
development of the borrower's load forecast, and load forecast updates. 
The approved load forecast work plan is intended to develop and maintain 
a process that will result in load forecasts that will meet the 
borrowers' own needs and the requirements of this subpart. An approved 
work plan represents a commitment by a power supply borrower and its 
members, or by a large unaffiliated distribution borrower, that all 
parties concerned will prepare their load forecasts in a timely manner 
pursuant to the approved load forecast work plan and they will modify 
the approved load forecast work plan as needed with RUS approval to 
address changing circumstances or enhance the usefulness of the approved 
load forecast work plan.
    (c) An approved load forecast work plan for a power supply borrower 
and its members must cover all member systems, including those that are 
not borrowers. However, only members that are borrowers, including the 
power supply borrower, are required to follow the approved load forecast 
work plan in preparing their respective load forecasts. Each borrower is 
individually responsible for forecasting all its RE Act beneficiary and 
non-RE Act beneficiary loads.
    (d) An approved load forecast work plan must outline the 
coordination and preparation requirements for both the power supply 
borrower and its members.
    (e) An approved load forecast work plan must cover a period of 2 or 
3 years depending on the applicable compliance filing schedule elected 
under Sec. 1710.204.
    (f) An approved load forecast work plan must describe the borrower's 
process and methods to be used in producing the load forecast and 
maintaining current load forecasts on an ongoing basis.
    (g) Approved load forecast work plans for borrowers with residential 
demand of 50 percent or more of total kWh

[[Page 118]]

must provide for a residential consumer survey at least every 5 years to 
obtain data on appliance and equipment saturation and electricity 
demand. Any such borrower that is experiencing or anticipates changes in 
usage patterns shall consider surveys on a more frequent schedule. Power 
supply borrowers shall coordinate such surveys with their members. 
Residential consumer surveys may be based on the aggregation of member-
based samples or on a system-wide sample, provided that the latter 
provides for relevant regional breakdowns as appropriate.
    (h) Approved load forecast work plans must provide for RUS review of 
the load forecasts as the load forecast is being developed.
    (i) A power supply borrower's work plan must have the concurrence of 
the majority of the members that are borrowers.
    (j) The borrower's board of directors must approve the load forecast 
work plan.
    (k) A borrower may amend its approved load forecast work plan 
subject to RUS approval. If RUS concludes that the existing approved 
load forecast work plan will not result in a satisfactory load forecast, 
RUS may require a new or revised load forecast work plan.