Sec. 1721.1  Advances.


    (a) Purpose and amount. With the exception of minor projects, 
insured loan funds will be advanced only for projects which are included 
in an RUS approved borrower's construction work plan (CWP) or approved 
amendment and in an approved loan, as amended. Loan fund advances can be 
requested in an amount representing actual costs incurred.
    (b) Minor project. Minor project means a project costing $100,000 or 
less. Such a project qualifies for advance of loan funds even though it 
may not have been included in an RUS-approved borrower's CWP, amendment 
to such CWP, or approved loan. Total advances requested shall not exceed 
the total loan amount. All projects for which loan fund advances are 
requested must be constructed to achieve purposes permitted by terms of 
the loan contract between the borrower and RUS.
    (c) Certification. Pursuant to the applicable provisions of the RUS 
loan contract, borrowers shall certify with each request for funds to be 
approved for advance that such funds are for projects in compliance with 
this section and shall also provide for those that cost in excess of 
$100,000, a contract or work order number as applicable and a CWP cross-
reference project coded identification number. For a minor project not 
included in an RUS approved borrower's CWP, the Borrower shall describe 
the project and do one of the following to satisfy RUS' environmental 
requirements (see 7 CFR part 1794).

[[Page 228]]

    (1) If applicable, state that the project is a categorical exclusion 
of a type described in Sec. 1794.21(b), which normally does not require 
preparation of an Environmental Report (ER); or
    (2) If applicable, state that the project is a categorical exclusion 
of a type that normally requires an ER and then:
    (i) Submit the ER with the request for funds to be approved for 
advance, or
    (ii) If applicable, certify that it has analyzed the minor project 
with respect to a comprehensive service area environmental map and data 
base collected and used in preparing the ER for its RUS-approved 
borrower's CWP, and that on the basis of that information, the minor 
project will not be located in an environmentally sensitive area or 
location.
    (d) Noncompliance. Where insured loan funds are found to have been 
advanced in noncompliance with this section, borrowers will be required 
to deposit the appropriate amount of the over-advance in the 
construction fund-trustee account and pay any accrued and unpaid 
interest to RUS. The Administrator will require borrowers, in order to 
remedy such noncompliance, to pay an additional amount equal to the 
interest on the funds over-advanced for the period such funds were 
outstanding, calculated at a rate equal to the difference between the 
RUS loan interest rate and the most recent rate at which RUS sold 
Certificates of Beneficial Ownership (CBO's). While RUS will generally 
permit the amount of over-advance deposited in the construction fund-
trustee account to be subsequently used by the borrower for RUS approved 
projects, nothing in this section shall be construed to preclude RUS 
from exercising any rights or remedies which RUS may have pursuant to 
the loan contract.

[64 FR 72489, Dec. 28, 1999]