[Code of Federal Regulations]
[Title 7, Volume 11]
[Revised as of January 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 7CFR1724.51]

[Page 236-238]
 
                          TITLE 7--AGRICULTURE
 
    CHAPTER XVII--RURAL UTILITIES SERVICE, DEPARTMENT OF AGRICULTURE
 
PART 1724--ELECTRIC ENGINEERING, ARCHITECTURAL SERVICES AND DESIGN POLICIES AND PROCEDURES--Table of Contents
 
                    Subpart E--Electric System Design
 
Sec. 1724.51  Design requirements.

    The provisions of this section apply to all borrower electric system 
facilities regardless of the source of financing.
    (a) Distribution. All distribution facilities must conform to the 
applicable RUS construction standards and utilize RUS accepted 
materials.
    (b) Transmission lines. (1) All transmission line design data must 
be approved by RUS.
    (2) Design data consists of all significant design features, 
including, but not limited to, transmission line design data summary, 
general description of terrain, right-of-way calculations, discussion 
concerning conductor and structure selection, conductor sag and tension 
information, design clearances,

[[Page 237]]

span limitations due to clearances, galloping or conductor separation, 
design loads, structure strength limitations, insulator selection and 
design, guying requirements, and vibration considerations. For lines 
composed of steel or concrete poles, or steel towers, in which load 
information will be used to purchase the structures, the design data 
shall also include loading trees, structure configuration and selection, 
and a discussion concerning foundation selection.
    (3) Line design data for uprating transmission lines to higher 
voltage levels or capacity must be approved by RUS.
    (4) Transmission line design data which has received RUS approval in 
connection with a previous transmission line construction project for a 
particular borrower is considered approved by RUS for that borrower, 
provided that:
    (i) The conditions on the project fall within the design data 
previously approved; and
    (ii) No significant NESC revisions have occurred.
    (c) Substations. (1) All substation design data must be approved by 
RUS.
    (2) Design data consists of all significant design features, 
including, but not limited to, a discussion of site considerations, oil 
spill prevention measures, design considerations covering voltage, 
capacity, shielding, clearances, number of low and high voltage phases, 
major equipment, foundation design parameters, design loads for line 
support structures and the control house, seismic considerations, 
corrosion, grounding, protective relaying, and AC and DC auxiliary 
systems. Reference to applicable safety codes and construction standards 
are also to be included.
    (3) Substation design data which has received RUS approval in 
connection with a previous substation construction project for a 
particular borrower is considered approved by RUS for that borrower, 
provided that:
    (i) The conditions on the project fall within the design data 
previously approved; and
    (ii) No significant NESC revisions have occurred.
    (d) Generating facilities. (1) This section covers all portions of a 
generating plant including plant buildings, the generator step-up 
transformer, and the transmission switchyard at a generating plant. 
Warehouses and equipment service buildings not associated with 
generation plants are covered under paragraph (e) of this section. 
Generation plant buildings must meet the requirements of paragraph 
(e)(1) of this section.
    (2) For all new generation units and for all repowering projects, 
the design outline shall be approved by RUS, unless RUS determines that 
a design outline is not needed for a particular project.
    (3) The design outline will include all significant design criteria. 
During the early stages of the project, RUS will, in consultation with 
the borrower and its consulting engineer, identify the specific items 
which are to be included in the design outline.
    (e) Headquarters--(1) Applicable laws. The design and construction 
of headquarters facilities shall comply with all applicable Federal, 
State, and local laws and regulations, including, but not limited to:
    (i) Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. 794), 
which states that no qualified individual with a handicap shall, solely 
by reason of their handicap, be excluded from participation in, be 
denied the benefits of, or be subject to discrimination under any 
program or activity receiving Federal financial assistance. The Uniform 
Federal Accessibility Standards (41 CFR part 101-19, subpart 101-19.6, 
appendix A) are the applicable standards for all new or altered borrower 
buildings, regardless of the source of financing.
    (ii) The Architectural Barriers Act of 1968 (42 U.S.C. 4151), which 
requires that buildings financed with Federal funds are designed and 
constructed to be accessible to the physically handicapped.
    (iii) The Earthquake Hazards Reduction Act of 1977 (42 U.S.C. 7701 
et seq.), and Executive Order 12699, Seismic Safety of Federal and 
Federally Assisted or Regulated New Building Construction (3 CFR 1990 
Comp., p. 269). Appropriate seismic safety provisions are required for 
new buildings for

[[Page 238]]

which RUS provides financial assistance. (See part 1792, subpart C, of 
this chapter.)
    (2) The borrower shall provide evidence, satisfactory in form and 
substance to the Administrator, that each building will be designed and 
built in compliance with all Federal, State, and local requirements.
    (f) Communications and control. (1) This section covers microwave 
and powerline carrier communications systems, load control, and 
supervisory control and data acquisition (SCADA) systems.
    (2) The performance considerations for a new or replacement master 
system must be approved by RUS. A master system includes the main 
controller and related equipment at the main control point. Performance 
considerations include all major system features and their 
justification, including, but not limited to, the objectives of the 
system, the types of parameters to be controlled or monitored, the 
communication media, alternatives considered, and provisions for future 
needs.