Sec. 1724.53  Preparation of plans and specifications.

    The provisions of this section apply to all borrower electric system 
facilities regardless of the source of financing.
    (a) General. (1) The borrower (acting through the engineer, if 
applicable) shall prepare plans and specifications that adequately 
represent the construction to be performed.
    (2) Plans and specifications for distribution, transmission, or 
generating facilities must be based on a construction work plan (as 
amended, if applicable), engineering study or construction program which 
has been approved by RUS if financing for the facilities will at any 
time be requested from RUS.
    (b) Composition of plans and specifications package. (1) Whether 
built by force account or contract, each set of plans and specifications 
must include:
    (i) Distribution lines. Specifications and drawings, staking sheets, 
key map and appropriate detail maps;
    (ii) Transmission lines. Specifications and drawings, transmission 
line design data manual, vicinity maps of the project, a one-line 
diagram, and plan and profile sheets;
    (iii) Substations. Specifications and drawings, including a one-line 
diagram, plot and foundation plan, grounding plan, and plans and 
elevations of structure and equipment, as well as all other necessary 
construction drawings, in sufficient detail to show phase spacing and 
ground clearances of live parts;
    (iv) Headquarters. Specifications and drawings, including:
    (A) A plot plan showing the location of the proposed building plus 
paving and site development;
    (B) A one line drawing (floor plan and elevation view), to scale, of 
the proposed building with overall dimensions shown; and
    (C) An outline specification including materials to be used (type of 
frame, exterior finish, foundation, insulation, etc.); and
    (v) Other facilities (e.g., generation and communications and 
control facilities). Specifications and drawings, as necessary and in 
sufficient detail to accurately define the scope and quality of work 
required.
    (2) For contract work, the appropriate standard RUS construction 
contract form shall be used as required by part 1726 of this chapter.