Sec. 1726.22  Methods of construction.

    The borrower is generally responsible for determining whether 
construction will be by contract or force account. If construction is by 
contract, the borrower must determine whether materials will be supplied 
by the contractor or will be furnished by the borrower. RUS reserves the 
right to require contract construction in lieu of force account 
construction on a case by case basis.