[Code of Federal Regulations]
[Title 7, Volume 11]
[Revised as of January 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 7CFR1726.35]

[Page 251-253]
 
                          TITLE 7--AGRICULTURE
 
    CHAPTER XVII--RURAL UTILITIES SERVICE, DEPARTMENT OF AGRICULTURE
 
PART 1726--ELECTRIC SYSTEM CONSTRUCTION POLICIES AND PROCEDURES--Table of Contents
 
                           Subpart A--General
 
Sec. 1726.35  Submission of documents to RUS.

    (a) Where to send documents. Documents required to be submitted to 
RUS under this part are to be sent to the office of the borrower's 
respective RUS Regional Director, the Power Supply Division Director, or 
such other office of RUS as designated by RUS (see part 1700 of this 
chapter.)
    (b) Borrower certification. When a borrower certification is 
required by this part, it must be made by the borrower's manager unless 
the board of directors specifically authorizes another person to make 
the required certification. In such case, a certified copy of the 
specific authorizing resolution must accompany the document or be on 
file with RUS.
    (c) Contracts requiring RUS approval. The borrower shall submit to 
RUS three copies of each contract that is subject to RUS approval under 
subparts B through F of this part. At least one copy of each contract 
must be an original signed in ink (i.e., no facsimile signature). Each 
contract submittal must be accompanied by:
    (1) A bid tabulation and evaluation and, if applicable, a written 
recommendation of the architect or engineer.
    (2) For awards made under the informal competitive bidding procedure 
or the multiparty negotiation procedure, a written recommendation of the 
contracting committee (See Secs. 1726.202 and 1726.203).
    (3) Three copies of an executed contractor's bond on RUS approved 
bond forms as required in the contract form (at least one copy of which 
must be an original signed in ink) and one copy of the bid bond or 
facsimile of the certified check.
    (4) A certification by the borrower or chairperson of the 
contracting committee, as applicable, that the appropriate bidding 
procedures were followed as required by this part.

[[Page 252]]

    (5) A certified copy of the board resolution awarding the contract.
    (6) Evidence of clear title to the site for substations and 
headquarters construction contracts, if not previously submitted.
    (7) Documentation that all reasonable measures were taken to assure 
competition if fewer than three bids were received.
    (d) Contract amendments requiring RUS approval. The borrower must 
submit to RUS three copies of each contract amendment (at least one copy 
of which must be an original signed in ink) which is subject to RUS 
approval under Sec. 1726.24(b). Each contract amendment submittal to RUS 
must be accompanied by:
    (1) A certified copy of the board resolution approving the 
amendment; and
    (2) A bond extension, where necessary.
    (e) Encumbrance of loan or loan guarantee funds. (1) For contracts 
subject to RUS approval, the submittals required under paragraph (c) of 
this section will initiate RUS action to encumber loan or loan guarantee 
funds for such contracts.
    (2) For contracts not subject to RUS approval (except for generation 
projects), loan or loan guarantee funds will normally be encumbered 
using RUS Form 219, Inventory of Work Orders, after closeout of the 
contracts. In cases where the borrower can show good cause for a need 
for immediate cash, the borrower may request encumbrance of loan or loan 
guarantee funds based on submittal of a copy of the executed contract, 
provided it meets all applicable RUS requirements.
    (3) For generation project contracts not subject to RUS approval, 
the borrower must submit to RUS the following documentation:
    (i) A brief description of the scope of the contract, including 
contract identification (name, number, etc.);
    (ii) Contract date;
    (iii) Contractor's name;
    (iv) Contract amount;
    (v) Bidding procedure used;
    (vi) Borrower certification that:
    (A) The board of directors approved the contract;
    (B) The bidding procedures and contract award for each contract were 
in conformance with the requirements of Part 1726, Electric System 
Construction Policies and Procedures;
    (C) If a RUS approved form of contract is required by this part, the 
terms and conditions of the RUS approved form of contract have not been 
altered;
    (D) If RUS has approved plans and specifications for the contract, 
the contract was awarded on the basis of those plans and specifications; 
and
    (E) No restriction has been placed on the borrower's right to assign 
the contract to RUS or its successors.
    (4) Contract amendments. (i) For amendments subject to RUS approval, 
the submittals required under paragraph (c) of this section will 
initiate RUS action to encumber loan or loan guarantee funds for 
contract amendments requiring RUS approval.
    (ii) For amendments not subject to RUS approval (except generation 
projects), loan or loan guarantee funds will normally be encumbered 
using RUS Form 219, Inventory of Work Orders, after closeout of the 
contracts. In cases where the borrower can justify a need for immediate 
cash, the borrower may request encumbrance of loan or loan guarantee 
funds based on submittal of a copy of the executed amendment, providing 
it meets all applicable RUS requirements.
    (iii) For each generation project contract amendment not subject to 
RUS approval, the borrower must submit to RUS the following information 
and documentation:
    (A) The contract name and number;
    (B) The amendment number;
    (C) The amendment date;
    (D) The dollar amount of the increase or the decrease of the 
amendment;
    (E) Borrower certification that:
    (1) The amendment was approved in accordance with the policy of the 
board of directors (the borrower must ensure that RUS has a certified 
copy of the board resolution establishing such policy);
    (2) If a RUS approved form of contract is required by this part, the 
terms and conditions of the RUS approved form of contract has not been 
altered; and

[[Page 253]]

    (3) No restriction has been placed on the borrower's right to assign 
the contract to RUS or its successors.