Sec. 1751.104  Obtaining RUS approval of a proposed Modernization Plan.

    (a) To obtain RUS approval of a proposed Modernization Plan, the 
Plan Developer must submit the following to RUS:
    (1) A certified copy of the statute or PUC order, if the PUC is the 
Plan Developer, or a written request for RUS approval of the proposed 
Modernization Plan signed by an authorized representative of the Plan 
Developer, if a majority of Borrowers is the Plan Developer; and
    (2) Three copies of the proposed Modernization Plan.
    (b) Generally, RUS will review the proposed Modernization Plan 
within (30) days and either:
    (1) Approve the Modernization Plan if it conforms to the provisions 
of this subpart in which case RUS will return a copy of the 
Modernization Plan with notice of approval to the Plan Developer; or
    (2) Not approve the proposed Modernization Plan if it does not 
conform to the provisions of this subpart. In this event, RUS will 
return the proposed Modernization Plan to the Plan Developer with 
specific written comments and suggestions for modifying the proposed 
Modernization Plan so that it will conform to the provisions of this 
subpart. If the Plan Developer remains eligible, RUS will invite the 
Plan Developer to submit a modified proposed Modernization Plan for RUS 
consideration. This process can continue until the Plan Developer gains 
approval of a proposed Modernization Plan unless the Plan Developer is a 
PUC whose eligibility has expired. If a PUC's eligibility has expired, 
RUS will return the proposed Modernization Plan unapproved. Because RUS 
does not have authority to extend the term of a PUC's eligibility, RUS 
recommends that the PUC submit a proposed Modernization Plan at least 90 
days in advance of February 13, 1996 to allow time for this process.