Sec. 1753.17  Engineering services.

    (a)(1) All engineering services required by a borrower to support 
its application for a loan shall be rendered by a qualified engineer 
selected by the borrower or by qualified employees on the borrower's 
staff. The selection of the preloan engineer, the form of preloan 
engineering service contract, and the contract itself, are not subject 
to RUS approval. Borrowers, however, should discuss their proposed 
method of obtaining preloan engineering services with the GFR before 
proceeding with any arrangements.
    (2) Form 835, Preloan Engineering Service Contract, Telephone System 
Design, is a suggested form of preloan engineering service contract. 
While use of this form of contract is not required, it will be helpful 
in determining the tasks to be performed. Any form of contract used 
shall specify that preloan engineering services conform to RUS 
requirements for preloan studies. See subpart D of 7 CFR part 1737.
    (b)(1) Major construction. (i) Three copies of Form 217 executed by 
the borrower and the engineer shall be sent to the GFR to forward to RUS 
for approval. The engineer's estimate of the engineering fees, on Form 
506, shall be included.
    (ii) RUS will review the contract terms and conditions. RUS will not 
approve the contract if, in RUS's judgement:
    (A) Unacceptable modifications have been made to the contract form.
    (B) The contract will not accomplish loan purposes.
    (C) The engineering service fees are unreasonable.
    (D) The contract presents unacceptable loan security risk to RUS.
    (E) The consulting engineering firm is affiliated with or has 
represented a contractor, vendor, or manufacturer who may provide labor, 
materials, or equipment to the borrower under any current loan.
    (2) Minor construction. When a borrower contracts for an engineering 
firm to inspect and certify construction accounted for under the work 
order procedure or the Contract for Miscellaneous Construction Work and 
Maintenance Services, Form 773 (See 7 CFR part 1753 subpart I), the 
borrower shall require that the certification be signed by a licensed 
engineer.
    (c)(1) Major construction. When the extent and complexity of the 
proposed construction is such that the engineering involved is within 
the capabilities of employees on the borrower's staff, borrowers may 
request RUS approval to provide such services.
    (i) The request shall include:
    (A) A description of services to be performed.
    (B) The name and qualifications of the employee to be in charge. RUS 
requires this employee to meet the State experience requirements for 
registered engineers. In the absence of specific State experience 
requirements, the employee must have at least eight years experience in 
the design and construction of telecommunication facilities, with at 
least two years of the work experience at a supervisory level. RUS does 
not require professional registration of this employee, but this does 
not relieve the borrower from compliance with applicable State 
registration requirements which may require a licensed individual to 
perform such services.
    (C) The names, qualifications, and responsibilities of other 
principal employees who will be associated with providing the 
engineering services.
    (D) A letter signed by an authorized representative of the borrower 
authorizing the engineering services to be performed by force account 
and certifying the information supporting the request.
    (ii) RUS shall notify the borrower by letter of approval or 
disapproval to perform force account engineering. The letter shall set 
forth any conditions associated with an approval or the reasons for 
disapproval.
    (iii) RUS's approval of force account engineering for major 
construction shall be only for the specific projects named in the notice 
of approval.
    (2) Minor construction. (i) When the borrower proposes to perform 
the inspection and certification of minor construction, the following 
shall be submitted to the RUS:
    (A) A copy of the employee's qualifications and experience record, 
unless previously submitted. RUS requires a minimum of four years of 
construction

[[Page 383]]

and inspection experience. The employee cannot be engaged in the actual 
construction.
    (B) A letter signed by an authorized representative of the borrower 
authorizing the performance of these services by the employee, subject 
to RUS approval, and certifying the supporting information.
    (ii) RUS shall notify the borrower by letter of approval or 
disapproval of the borrower's staff employee to perform the inspection 
and certification of construction. The approval shall be limited to the 
employee's area of expertise.
    (d)(1) Subject to the requirements of this part and other applicable 
regulations, RUS will make loan funds available for the architectural 
and engineering services up to the amounts included in the approved 
loan.
    (2) Advance of funds shall be requested on an FRS as set forth in 7 
CFR part 1744 subpart C.
    (e) The borrower shall obtain status of contract and force account 
proposal reports from the engineer once each month. The report shall 
show for each contract or FAP the approved contract or FAP amount, the 
date of approval, the scheduled date construction was to begin and the 
actual date construction began, the scheduled completion date, the 
estimated or actual completion date, the estimated or actual date of 
submission of closeout documents, and an explanation of delays or other 
pertinent data relative to progress of the project. One copy of this 
report shall be submitted to the GFR.
    (f)(1) Upon completion of all services required under the 
engineering service contract Form 217, the borrower shall obtain from 
the engineer four copies of the Final Statement of Engineering Fee, Form 
506.
    (2) If the statement is satisfactory, the borrower shall sign all 
copies and send three to the GFR.
    (3) After RUS approval of Form 506, one copy shall be sent to the 
borrower and one copy sent to the engineer.
    (4) The borrower shall promptly make final payment to the engineer.

[54 FR 3984, Jan. 27, 1989. Redesignated at 55 FR 39397, Sept. 27, 1990, 