                           Subpart A--General
 
Sec. 1753.2  Definitions.

    For the purpose of this part 1753:
    Alternate-- A solicitation for a bid adjustment for a specified 
deviation from the Plans and Specifications.
    Architect-- A person registered as an architect in the state where 
construction is performed, or a person on the borrower's staff, approved 
by RUS, authorized to perform architectural services.
    Bid guarantee-- A bid bond or certified check required of 
contractors bidding on construction work to ensure that the bidder, if 
successful, will furnish a satisfactory performance bond ensuring 
completion of work.
    Central office building-- The facility housing the central office 
equipment.
    Central office equipment-- Switching and signaling equipment that 
performs call origination and completion functions for subscribers.
    Closeout documents-- The documents required to certify satisfactory 
completion of all obligations under a contract or force account 
proposal.
    Construction-- Purchase and installation of telecommunications 
facilities in a borrower's system using loan funds.
    Contract-- The agreement between the borrower and an independent 
contractor covering the purchase, construction, or both of telephone 
facilities to be included in the borrower's telephone system.
    Contract construction-- Construction and installations performed 
using an RUS contract form. See 7 CFR 1755.93.
    Engineer-- A person registered as an engineer in the state where 
construction is performed, or a person on the borrower's staff, approved 
by RUS, authorized to perform engineering services.
    FAP (force account proposal)--The borrower's detailed plans 
submitted to RUS for force account construction.
    Force account construction--Construction performed by the borrower's 
employees under an RUS approved FAP,

[[Page 374]]

with the borrower furnishing all materials, equipment, tools, and 
transportation.
    FRS--RUS Form 481 (OMB control number 0572-0023), Financial 
Requirement Statement.
    GFR--RUS General Field Representative.
    Installation--The act of setting up or placing in position equipment 
for service or use in the borrower's system.
    Interim construction--The purchase of equipment or the conduct of 
construction under an RUS-approved plan of interim financing. See 7 CFR 
part 1737.
    Interim financing--Funding for a project which RUS has acknowledged 
may be included in a loan, should said loan be approved, but for which 
RUS loan funds have not yet been made available.
    Labor and materials--All the labor and materials required for 
construction.
    LD (loan design)--Supporting data for a loan application. See 7 CFR 
part 1737.
    Loan--Any loan made or guaranteed by RUS. See 7 CFR part 1735.
    Loan funds--Funds provided by RUS through direct or guaranteed 
loans. See 7 CFR part 1744 subpart C.
    Loan purposes--The high level objectives of the loan are to fund the 
construction. These purposes are first stated in the characteristics 
letter described in 7 CFR 1737.80, which is sent to the applicant to 
offer a loan after RUS has completed its preloan studies.
    Major construction--A telecommunications plant project estimated to 
cost more than $250,000, including all labor and materials.
    Minor construction--A telecommunications plant project estimated to 
cost $250,000 or less, including all labor and materials.
    Minor errors or irregularities--A defect or variation in a seller's 
bid that is a matter of form and not of substance. Errors or 
irregularities are ``minor'' if they can be corrected or waived without 
being prejudicial to other bidders and when they do not affect the 
price, quantity, quality, or timeliness of construction. Unless 
otherwise noted, the borrower determines whether an error or 
irregularity is ``minor.''
    Modernization plan--A State plan, which has been approved by RUS, 
for improving the telecommunications network of those Telecommunications 
Providers covered by the plan. A Modernization Plan must conform to the 
provisions of 7 CFR part 1751, subpart B.
    Negotiation--Any form of purchasing or contracting other than sealed 
competitive bidding. Any contract awarded without using the sealed 
competitive bidding procedure is a negotiated contract.
    Outside plant--The facilities that conduct electrical or optical 
signals between the central office and the subscriber's network 
interface or between central offices.
    Performance bond--A surety bond on a form satisfactory to RUS 
guaranteeing the contractor's faithful performance of a contract.
    P&S (plans and specifications)--An RUS contract form, the 
appropriate specifications, and such additional information and 
documents needed to provide a clear, accurate, and complete 
understanding of the installations to be made or construction to be 
performed.
    Project--The construction or installation described in the P&S.
    Responsive bid--A bid that complies with the requirements of the 
plans and specifications.
    RTB--the Rural Telephone Bank, established as a body corporate and 
an instrumentality of the United States, to obtain supplemental funds 
from non-Federal sources and utilize them in making loans, for the 
purposes of financing, or refinancing, the construction, improvement, 
expansion, acquisition, and operation of telephone lines, facilities, or 
systems, for RUS borrowers financed under sections 201 and 408 of the 
Act.
    RUS--the Rural Utilities Service, an agency of the United States 
Department of Agriculture established pursuant to Section 232 of the 
Federal Crop Insurance and Reform and Department of Agriculture 
Reorganization Act of 1994 (Pub. L. 103-354, 108 Stat. 3178), successor 
to Rural Electrification Administration with respect to administering 
certain electric and telecommunications program. See 7 CFR 1700.1.

[[Page 375]]

    Sealed competitive bidding--A method of contracting that employs 
sealed competitive bids, public opening of bids, and award of the 
contract to the bidder submitting the lowest responsive bid. See 
Sec. 1753.8.
    Single source negotiation--Negotiating with a single source 
(contractor or seller).
    Special equipment--Equipment used primarily for the transmission and 
enhancement of voice, data, carrier, radio and light signals, and other 
equipment and facilities, including incidental cable and other 
transmission equipment.
    Subcontract--A secondary contract undertaking some of the 
obligations of a primary contract. Under all RUS forms of contract, the 
primary contractor bears full responsibility for the performance of the 
subcontractor.
    Unbalanced bid--A bid which contains pricing for a task or material 
that is significantly higher or lower than pricing for similar tasks or 
materials.
    Work order construction--Minor construction performed by the 
borrower's employees, pursuant to its work order procedure, with the 
borrower furnishing all materials, equipment, tools, and transportation.

[54 FR 39267, Sept. 25, 1989, unless otherwise noted. Redesignated at 55 
FR 39396, Sept. 27, 1990, and amended at 58 FR 66259, Dec. 20, 1993; 59 
FR 17464, Apr. 13, 1994; 64 FR 16604, Apr. 6, 1999]