Sec. 1753.29  Force account procedures.

    (a) The borrower must obtain RUS approval of the force account 
method of construction of buildings in advance in order to obtain RUS 
financing.
    (b) The borrower shall prepare the P&S in accordance with 
Sec. 1753.26.
    (c) Prior to any construction activity or the purchase of materials 
or equipment, the borrower shall submit the FAP in duplicate to RUS, 
accompanied by a resolution indicating approval of the board of 
directors of the borrower or a letter signed by an authorized corporate 
official. The proposal shall include:
    (1) A Copy of the P&S.
    (2) An itemized list of all items of materials required for 
construction.
    (3) A construction schedule showing the estimated construction 
period for each major construction item.
    (4) An estimate of the material and labor and other costs for any 
construction item not provided for in the approved loan.
    (d) Force Account construction to be financed with loan funds shall 
not be started until RUS approval has been received by the borrower.