Sec. 1753.39  Closeout documents.

    Closeout of RUS Contract Form 525, Central Office Equipment Contract 
(Including Installation), and RUS Contract Form 545, Central Office 
Equipment Contract (Not Including Installation), shall be conducted as 
follows:
    (a) Contract amendments. Amendments that must be submitted to RUS 
for approval, as required by Sec. 1753.11, shall be submitted promptly. 
All other amendments may be submitted to RUS with the engineer's 
contract closeout certification.
    (b) Taxes. Under the terms of RUS Contract Forms 525 and 545, the 
bid prices do not include any amounts which are or may be payable by the 
bidder or the borrower on account of taxes imposed upon the sale, 
purchase or use of equipment, material and software covered by the 
contracts. If any such tax is paid by the bidder, the contract requires 
that the amount is to be stated separately on all invoices and paid by 
the borrower.
    (c) Acceptance tests. The borrower will perform acceptance tests as 
part of the partial closeout and final closeout of RUS Contract Form 
525. Tests that will demonstrate compliance with the requirements of 7 
CFR 1755.522 are contained in RUS Bulletin 1753E-201. Other tests 
demonstrating compliance will be acceptable. RUS Bulletin 1753E-201 is 
available from RUS, Program Support and Regulatory Analysis, STOP 1522, 
1400 Independence Ave., SW., Washington, DC 20250-1522.
    (d) Grounding system audit. A grounding system audit shall be 
performed and found acceptable for equipment provided under Form 525 and 
545 Contracts, prior to placing a central office or remote switching 
terminal into full service operation. The audits are to be conducted in 
accordance with guidelines contained in the applicable sections of RUS 
Form 522 ``General Specification for Digital, Stored Program Controlled 
Central Office Equipment.'' The audits shall be performed by the 
contractor and borrower for Form 525 equipment and by the borrower for 
Form 545 equipment.
    (e) Partial Closeout Procedure. Under conditions set forth in RUS 
Contract Form 525, a contractor may, when approved by the borrower, 
receive payment in full for central offices and their respective 
associated remote switching terminals upon completion of the 
installation without awaiting completion of the project where the 
contractor is to receive such payment, the procedure contained in the 
applicable sections of RUS Contract Form 525 shall be followed. In 
addition to complying with the appropriate partial

[[Page 394]]

closeout procedure contained in RUS Contract Form 525, the borrower 
shall:
    (1) Obtain from the engineer a certification of partial closeout.
    (2) Submit one copy of the summary to RUS with an FRS.
    (f) Final contract closeout procedure. The documents required for 
the final closeout of the central office equipment contract, RUS 
Contract Forms 525 and 545, are listed in the following table, which 
also indicates the number of copies and their distribution. The 
procedure to be followed is as follows:

                        Documents Required To Closeout Central Office Equipment Contract
----------------------------------------------------------------------------------------------------------------
                                            Use with                 Prepared by              Distribution
                                   -----------------------------------------------------------------------------
  RUS Form No.      Description       RUS Form     RUS Form
                                        525          545       Contractor    Engineer     Borrower    Contractor
----------------------------------------------------------------------------------------------------------------
238............  Construction or              X            X  ...........          (3)     (to RUS)     (to RUS)
                  Equipment
                  Contract
                  Amendment (if
                  not previously
                  submitted, send
                  to RUS for
                  approval).
754............  Certificate of               X  ...........            3            3            2            1
                  Completion and
                  Certificate of
                  Contractor and
                  Indemnity
                  Agreement (if
                  submitted, Form
                  744 is not
                  required).
517............  Results of                   X  ...........  ...........            2            1            1
                  Acceptance Tests
                  (prepare and
                  distribute
                  copies
                  immediately upon
                  completion of
                  the acceptance
                  tests of each
                  central office).
752a...........  Certificate of     ...........            X  ...........            2            1            1
                  Completion--Not
                  Including
                  Installation.
224............  Waiver and                   X  ...........            1  ...........            1  ...........
                  Release of Lien
                  (from each
                  supplier).
231............  Certificate of               X  ...........            1  ...........            1  ...........
                  Contractor.
213............  Certificate (Buy             X            X            1  ...........            1  ...........
                  American).
None...........  Switching                    X            X            2  ...........            2  ...........
                  Diagram, as
                  installed.
None...........  Set of Drawings              X            X            2  ...........            2  ...........
                  (each set to
                  include all the
                  drawings
                  required under
                  the
                  Specification,
                  RUS Form 522).
----------------------------------------------------------------------------------------------------------------

    (1) The borrower shall:
    (i) Immediately following completion of the last central office 
equipment installation, arrange with the contractor's installer, 
connecting company (where necessary), and the GFR for performance of the 
acceptance tests of offices not previously tested. The date for testing 
should be established so that the installer will not be required to 
return to the site for the sole purpose of assisting in these tests. 
Acceptance tests shall be performed within 30 days of completion of the 
installation, unless otherwise requested in writing by the contractor 
and approved in writing by the borrower.
    (ii) When the acceptance tests have been satisfactorily completed 
and the contractor has corrected all the discrepancies:

[[Page 395]]

    (A) Prepare and assemble the documents listed in the table in this 
section, Documents Required to Close Out Central Office Equipment 
Contracts.
    (B) Notify the GFR that the project is ready for final RUS 
inspection.
    (iii) Make the documents listed in the table available for GFR 
review on the date of final inspection.
    (iv) Distribute the documents as indicated in the table. The 
documents listed for RUS shall be retained by the borrower for 
inspection by RUS for at least two years from the date of the engineer's 
contract closeout certificate.
    (2) The documents required and the procedure to be used for 
equipment purchased and/or installations made using the method of minor 
construction are set forth in subpart I.
    (g) Once RUS approval has been obtained for any required amendments, 
the borrower shall obtain certifications from the engineer that the 
project and all required documentation are satisfactory and complete. 
The requirements for the final contract certification are contained in 
Sec. 1753.18.
    (h) Once these certifications have been received, final payment 
shall be made according to the payment terms of the contract. Copies of 
the certifications shall be submitted with the FRS, requesting the 
remaining funds on the contract.

[54 FR 39267, Sept. 25, 1989. Redesignated at 55 FR 39397, Sept. 27, 
1990, and amended at 59 FR 31126, June 17, 1994; 59 FR 43717, Aug. 25, 
1994; 62 FR 32477, June 16, 1997; 64 FR 16608, Apr. 6, 1999]