Sec. 1753.47  Plans and specifications (P&S).

    (a) General. (1) Prior to the preparation of P&S for the 
construction project:
    (i) A review shall be made of the outside plant requirements, and 
the Loan Design (LD) shall be revised to reflect any needed changes (See 
Sec. 1753.3).
    (ii) Deviations from the approved LD (7 CFR part 1737) must be 
approved by RUS (See Sec. 1753.3).
    (2) The standard RUS specifications required for construction of 
outside plant facilities are:
    (i) RUS Form 515a (Bulletin 345-150)--Specifications and Drawings 
for Construction of Direct Buried Plant.
    (ii) RUS Form 515c (Bulletin 345-151)--Specifications and Drawings 
for Conduit and Manhole Construction.
    (iii) RUS Form 515d (Bulletin 345-152)--Specifications and Drawings 
for Underground Cable Installation.
    (iv) RUS Form 515f (Bulletin 345-153)--Specifications and Drawings 
for Construction of Pole Lines and Aerial Cables.

[[Page 396]]

    (v) RUS Form 515g (Bulletin 345-154)--Specifications and Drawings 
for Service Entrance and Station Protector Installation.
    (b) Preparation of plans and specifications. Each set of plans and 
specifications shall include:
    (1) RUS Contract Form 515, ``Telephone System Construction Contract 
(Labor and Materials).''
    (2) The specifications described in paragraph (a)(2) of this section 
as specified by the borrower in the RUS Contract Form 515.
    (3) Description of special assembly units and guide drawings, if 
any.
    (4) Key, detail, and cable layout maps.
    (5) RUS Contract Form 787, ``Supplement A to Construction Contract, 
RUS Contract Form 515,'' when the borrower proposes to provide any 
materials to the contractor. The borrower shall not order materials for 
a contractor without RUS approval. In such cases the borrower must 
attach Form 787 and a ``List of Owner's Materials on Hand'' and/or a 
``List of Materials Ordered by Owner but Not Delivered'' to contract 
Form 515 (See Sec. 1753.48(f) of this part). Any materials furnished 
under Supplement A shall be listed in RUS Bulletin 344-2 unless special 
RUS approval has been received by the borrower to use unlisted 
materials.
    (c) Submission of plans and specifications to RUS. (1) If the 
project does not exceed $500,000 or 25% of the loan, whichever is less, 
the borrower shall furnish GFR one set of P&S. The borrower may then 
proceed with procurement in accordance with Sec. 1753.48.
    (2) If the project exceeds $500,000 or 25% of the loan, whichever is 
less, RUS approval of P&S is required. Two sets of P&S shall be 
furnished to GFR. RUS will return one set to the borrower upon notice of 
approval. The borrower may then proceed with procurement in accordance 
with Sec. 1753.48.

[54 FR 39267, Sept. 25, 1989. Redesignated at 55 FR 39397, Sept. 27, 
1990, 55 FR 53488, Dec. 31, 1990; 64 FR 16609, Apr. 6, 1999]