Sec. 1753.48  Procurement procedures.

    (a) Sealed competitive bidding--(1) Qualifying bidders. (i) The 
borrower is responsible for selecting qualified contractors to bid on 
the project. See Sec. 1753.8(a)(3). Questions relating to bidders' 
qualifications shall be resolved prior to the pre-bid conference.
    (ii) RUS Form 274 or its equivalent, supplemented by RUS Form 276, 
shall be used for the submission of bidders' qualifications for all 
types of construction and for the required information on the bidder and 
subcontractors.
    (2) Invitations to bid-- The borrower shall solicit bids as set 
forth in Sec. 1753.8(a)(2). Invitations shall be sent to at least 6 
prospective bidders.
    (3) Pre-bid conference. (i) Representatives of the borrower and its 
engineer shall be present at the pre-bid conference at the time and 
place designated in the Notice to Bidders. The borrower shall invite the 
GFR to attend the pre-bid conference.
    (ii) The purpose of the pre-bid conference is to acquaint the 
bidders with the scope and special considerations of the project and to 
clarify any concerns the bidders may have.
    (iii) No proposals shall be considered from bidders that do not 
attend the pre-bid conference unless the bidder has been notified by the 
engineer that such bidder's attendance has been waived. Attendance can 
be waived if, in the judgment of the engineer, the bidder would gain no 
additional understanding of the construction project by attending the 
pre-bid conference.
    (iv) The borrower shall obtain from the engineer the minutes of the 
pre-bid conference and shall distribute them to all potential bidders.
    (v) When fewer than three bidders have been qualified to submit 
bids, RUS written approval must be obtained to proceed with requesting 
bids.
    (4) Bid openings. (i) Bid openings and award of the contract shall 
be conducted in accordance with Secs. 1753.5(b)(1) and 1753.8(a).
    (ii) If Sec. 1753.8 requires RUS approval of award of the bid, the 
borrower shall submit to RUS two copies of the assembly unit sections of 
the apparent lowest responsive bid accepted by the borrower.
    (b) Negotiated procurement. (1) Competitive bids are not required 
for outside plant construction that is estimated to cost $250,000, or 
less, inclusive of labor and materials.

[[Page 397]]

    (2) The procedures to be followed are contained in Sec. 1753.8(b) 
and paragraphs (3) and (4) of this section.
    (3) Negotiation conference. (i) The borrower shall schedule a 
conference to be attended by representatives of the engineer, the 
borrower and the contractor selected for negotiations. The borrower 
shall invite the GFR to attend this conference.
    (ii) The purpose of the negotiation conference is to acquaint the 
contractor with the scope and special considerations of the project and 
to answer any questions.
    (iii) The borrower shall obtain from the engineer notes covering the 
negotiation conference and shall distribute them to all attendees.
    (4) Two copies of the assembly unit sections of the negotiated 
contractor's proposal shall be sent to the GFR for approval.
    (c) Contract amendments. The borrower shall prepare contract 
amendments in accordance with Sec. 1753.11 on RUS Contract Form 526, 
Construction Contract Amendment.
    (d) Subcontracts. The RUS requirements for subcontracts and the 
procedures to be followed are set forth in Sec. 1753.9.
    (e) Preconstruction conference. The borrower shall conduct a 
conference, attended by the borrower, contractor, subcontractors, 
resident engineer, and the GFR, prior to the beginning of cable 
placement, to resolve any questions pertaining to the construction. 
Results of the conference shall be provided to each conference 
participant (See Sec. 1753.10).
    (f) Owner-furnished materials. When the borrower furnishes materials 
under RUS Contract Form 787, Supplement A to Construction Contract, 
these steps shall be followed:
    (1) Materials on hand to be furnished by the borrower shall be 
released to the contractor at the start of construction. Materials on 
order but not received shall be provided to the contractor as they 
become available. The borrower shall obtain from the contractor a 
written receipt for all such materials delivered.
    (2) Materials on hand, until released to the contractor, shall be 
covered by fire and either wind-storm or extended coverage insurance, 
exclusive of materials stored in the open and not within 100 feet of any 
building. Poles, wherever stored, shall be covered by fire insurance. 
All insured values must be at least 80 percent of the cash value of the 
property insured.
    (3) Subject to adjustment at the time of final settlement, the 
borrower shall obtain from the contractor monthly invoices that show 
credit to the borrower, at the prices quoted in Form 787, Supplement A, 
for all materials furnished by the borrower and installed by the 
contractor during the preceding month.
    (4) Any materials furnished by the borrower remaining as surplus at 
the completion of construction shall be returned to the borrower. For 
such materials, the borrower shall furnish a written receipt to the 
contractor and credit the contractor at the prices quoted in Supplement 
A.
    (g) Changes or corrections in construction. (1) When changes or 
corrections in construction are necessary, and the cost of such changes 
or corrections is properly chargeable to the borrower, the borrower 
shall have its engineer prepare and sign four copies of a Construction 
Change Order, RUS Form 216, obtain borrower's approval and forward the 
four copies to the contractor. Receipt of the executed Construction 
Change Order by the contractor will constitute authorization to proceed 
with the changes or corrections.
    (2) When the changes or corrections have been made, the borrower 
shall have the contractor complete the form, itemizing the costs in 
accordance with the terms of the contract, and return three copies to 
the borrower's engineer. A copy of each change order shall be attached 
to each copy of the construction inventory required to close out the 
contract.