Sec. 1753.58  Closeout documents.

    (a) General. (1) This section outlines the procedure to be followed 
in the preparation of closeout documents for the FAP.
    (2) The period between the completion of construction and submission 
of the closeout documents to RUS should not exceed 60 days.
    (b) Documents. The documents required to close the FAP are listed in 
the following table. The following is a brief description of the 
closeout documents:

Documents Required To Close Out Force Account Outside Plant Construction
------------------------------------------------------------------------
         RUS Form No.                         Description
------------------------------------------------------------------------
817, 817a, 817b..............  Final Inventory Force Account
                                Construction and Certificate of
                                Engineer. Submit one copy to RUS, if
                                required \1\
213..........................  Certificate--``Buy American'' (as
                                applicable from each supplier).
None.........................  Detail Maps.
None.........................  Key map, if applicable.
None.........................  Staking Sheets.
None.........................  Tabulation of staking sheets.
None.........................  Treated Forest Products Inspection
                                Reports or Certificates of Compliance
                                (prepared by inspection company or
                                supplier).
------------------------------------------------------------------------
\1\ RUS Forms 817, 817a, and 817b are to be submitted to GFR only if
  required in paragraph (c)(5) of this section. Otherwise, the final
  inventory documents are to be assembed and retained by the borrower
  for at least two years.

    (c) Closeout procedures. (1) The borrower shall notify the GFR when 
the project is ready for final inspection.
    (2) The GFR shall be invited to make the final inspection 
accompanied by the engineer and the borrower.
    (3) The borrower shall correct all deficiencies found during the 
final inspection.
    (4) The borrower may request the assistance of an RUS field 
accountant to review the borrower's record of construction expenditures 
and assist the borrower with any accounting problems in connection with 
construction expenditures.
    (5) After inspection, the final inventory documents shall be 
assembled as indicated in the table in this section. RUS Forms 817, 
817a, and 817b are to be submitted to GFR only if the amount of the 
closeout exceeds the original force account proposal by 20% or more. 
Otherwise, the final inventory documents are to be assembed and retained 
by the borrower for at least two years.
    (6) Upon approval of the closeout documents, RUS will notify the 
borrower of approval and of any adjustments to be made in funds advanced 
in connection with the construction.
    (d) The above are not intended to be a complete description of the 
requirements of the documents relating to RUS's closeout procedure. 
Refer to the documents for additional requirements.