[Code of Federal Regulations]
[Title 7, Volume 11]
[Revised as of January 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 7CFR1753.68]

[Page 402-405]
 
                          TITLE 7--AGRICULTURE
 
    CHAPTER XVII--RURAL UTILITIES SERVICE, DEPARTMENT OF AGRICULTURE
 
PART 1753--TELECOMMUNICATIONS SYSTEM CONSTRUCTION POLICIES AND PROCEDURES--Table of Contents
 
        Subpart H--Purchase and Installation of Special Equipment
 
Sec. 1753.68  Purchasing special equipment.

    (a) General. (1) Equipment purchases are categorized as initial 
equipment purchase, equipment additions to existing systems and new 
system additions.
    (i) An initial equipment purchase is a first time purchase by a 
borrower of a complete system of special equipment.
    (ii) Equipment additions to existing systems are additions of 
components to complete operating systems to increase system capacity 
that require components made by the manufacturer of the existing system.
    (iii) New system additions are purchases of complete systems of 
special equipment when the purpose can be accomplished either with 
equipment of the same type and manufacture as other complete operating 
systems in the borrower's system, or with complete systems of special 
equipment from other manufacturers.
    (iv) Where equipment is obtained under a Form 398 Contract, the 
borrower shall require the supplier to provide a detailed proposed 
bonding and

[[Page 403]]

grounding plan and detailed installation information. The installation 
information is to enable acceptance testing by the borrower upon 
completion of the installation.
    (2) For initial equipment purchases that qualify as major 
construction, the borrower shall obtain proposals from at least three 
suppliers of equipment of different manufacturers.
    (3) For equipment additions to increase the capacity of existing 
systems, the borrower may negotiate for equipment of a specific type and 
manufacture. RUS approval to negotiate in this instance is not required 
if these additions were specifically described in the LD approved by RUS
    (4) For new system additions, the borrower may request RUS approval 
to negotiate for additional equipment for the purpose of standardization 
on a system basis, provided RUS approved the procurement method used for 
the initial equipment purchase. RUS approval to negotiate must be 
obtained before release of the P&S to the seller.
    (5) RUS will not approve negotiation with a seller of non-domestic 
equipment for the purpose of standardization, because such a purchase 
does not meet the ``Buy American'' provision.
    (6) RUS recommends, but does not require, that borrowers include 
installation by the seller for initial installations of special 
equipment that qualify as major construction.
    (7) Special equipment may be installed by the borrower if it has 
qualified personnel and test equipment available to install the 
equipment and make the required acceptance tests, and written approval 
is given by RUS.
    (8) Installations, whether by the borrower or the seller, must meet 
the installation requirements of Form 397 specifications. A copy of the 
acceptance tests results must be attached to the closeout documents or 
work order summary.
    (9) Detailed considerations and guidelines for the preparation of 
the specifications for the various applications of special equipment can 
be found in RUS Telecommunications Engineering and Construction Manuals.
    (10) The borrower must obtain authorization from the Federal 
Communications Commission (FCC) to construct and operate radio 
transmitting equipment. Evidence of FCC authorization is required for 
RUS contract approval. Where required, the borrower must obtain approval 
of state regulatory bodies regarding tariffs and related matters.
    (b) Procurement procedures--(1) General. The following are the 
procurement procedure steps required for the purchase of special 
equipment by borrowers.
    (2) Initial equipment purchase. (i) The borrower prepares P&S and, 
for projects estimated to exceed $500,000 or 25% of the loan, whichever 
is less, sends two copies to GFR for approval.
    (ii) For projects estimated to exceed $500,000 or 25% of the loan, 
whichever is less, RUS will either approve P&S in writing or notify the 
borrower of the reasons for withholding approval.
    (iii) For projects estimated to cost less than $500,000 or 25% of 
the loan, whichever is less, the borrower may proceed with procurement 
upon completion of the P&S.
    (iv) If the borrower has employed full competitive bidding in the 
selection, a contract may be executed with the successful bidder and the 
borrower may proceed to paragraph (b)(2)(vi) of this section.
    (v) If the borrower did not follow a fully competitive bidding 
process as described in Sec. 1753.8, the selection, along with a summary 
of all proposals and an engineer's recommendation, shall be sent to RUS. 
RUS shall approve the proposal selection in writing or notify the 
borrower of any reason for withholding approval.
    (vi) The borrower sends three executed contracts including 
specifications to RUS for approval.
    (vii) After RUS approval of the contract, one copy will be returned 
to the borrower and one copy will be sent to the seller.
    (3) Equipment additions to existing systems. Purchase procedures for 
equipment additions to existing systems are the same as for initial 
system purchase except that the borrower may negotiate for equipment of 
a specific type and manufacture instead of obtaining proposals from 
three or more sellers.
    (4) New system additions. (i) The borrower prepares the P&S and, if 
the

[[Page 404]]

project is estimated to exceed $500,000 or 25% of the loan, whichever is 
less, sends two copies to the GFR for approval. The borrower may request 
RUS approval to negotiate for the purpose of standardization on a system 
basis prior to preparing the P&S.
    (ii) RUS notifies the borrower in writing as to whether the borrower 
may negotiate for specific equipment. If P&S were required to be 
submitted to RUS under paragraph (b)(4)(i) of this section, RUS notifies 
the borrower in writing of P&S approval (or notifies the borrower of the 
reasons for withholding approval).
    (iii) The remainder of the purchase procedure for new system 
additions is the same as for initial equipment purchase.
    (c) Contract amendments. (1) The general requirements for contract 
amendments are set forth in Sec. 1753.11.
    (2) The borrower shall prepare any required amendments to the 
special equipment contract, arrange for the execution by all parties, 
and submit these amendments to RUS in accordance with Sec. 1753.11(d). 
RUS Form 238, Construction or Equipment Contract Amendment, shall be 
used for this purpose.
    (d) Closeout procedures--(1) Acceptance tests for Form 397. (i) 
Immediately upon completion of the installation and alignment of the 
equipment, the borrower shall arrange with the contractor's installer 
and the GFR for acceptance tests.
    (ii) The borrower shall obtain from the contractor, in writing, the 
results of all inspections and tests made by the contractor as required 
in the specifications. The borrower will analyze the test results and 
determine whether the performance of the equipment meets the contract 
specifications.
    (2) Acceptance tests for Form 398. (i) Upon completion of the 
installation and alignment of the equipment (under this contract the 
installation alignment will be by other than the seller) the borrower 
shall perform all the inspections and tests outlined in the 
specifications.
    (3) Closeout documents. When the acceptance tests have been 
completed and all deficiencies have been corrected, the borrower:
    (i) Assembles and distributes the documents listed in the following 
table that are required for the closeout of the special equipment 
contract. The documents listed for RUS shall be retained by the borrower 
for inspection by RUS for at least two years from the date of the 
engineer's contract closeout certification.

                           Documents Required To Close Out Special Equipment Contracts
                                             [RUS Forms 397 and 398]
----------------------------------------------------------------------------------------------------------------
                                          No. of copies prepared by                           Distribution
  RUS Form No.      Description    ---------------------------------------   Engineer  -------------------------
                                      Form 397     Form 398    Contractor                 Borrower    Contractor
----------------------------------------------------------------------------------------------------------------
238              Construction or    ...........          (3)  ...........          (3)     (to RUS)     (to RUS)
                  Equipment
                  Contract
                  Amendment (if
                  not previously
                  submitted, send
                  to RUS for
                  approval).
396              Certificate of     ...........            2  ...........  ...........            1            1
                  Completion--
                  Special
                  Equipment
                  Contract
                  (Including
                  Installation).
396a             Certificate of     ...........  ...........  ...........            2            1            1
                  Completion--
                  Special
                  Equipment
                  Contract (Not
                  Including
                  Installation).
744              Certificate of               1  ...........  ...........  ...........            1  ...........
                  Contractor and
                  Indemnity
                  Agreement.
213              Certificate (Buy             1  ...........            1  ...........            1  ...........
                  American).

[[Page 405]]


None             Report in                    1  ...........  ...........            1            1  ...........
                  writing,
                  including all
                  measurements and
                  other
                  information
                  required under
                  Part II of the
                  applicable
                  specifications.
None             Set of                       1  ...........            1  ...........            1  ...........
                  maintenance
                  recommendations
                  for all
                  equipment
                  furnished under
                  the contract.
----------------------------------------------------------------------------------------------------------------

    (ii) Obtains certifications from the engineer that the project and 
all required documentation are satisfactory and complete. Requirements 
for this contract closeout certification are contained in Sec. 1753.18.
    (iii) Submits copies of the engineer's certifications to RUS with 
the FRS requesting the remaining funds on the contract.
    (iv) Makes final payment in accordance with the payment terms of the 
contract.

[54 FR 39267, Sept. 25, 1989. Redesignated at 55 FR 39397, Sept. 27, 
1990, and amended at 59 FR 43718, Aug. 25, 1994; 64 FR 16611, Apr. 6, 
1999]