  Subpart C--Program Planning, Application and Modification Procedures
 
Sec. 632.22  Modification of a Comprehensive Annual Plan (CAP) and/or Master Plan.

    (a) The requirements for modifying a Master Plan and/or CAP will be 
included in administrative instructions issued by the Grant Officer upon 
final implementation of the Master Plan/CAP system.
    (b) Prior to implementing the Master Plan/CAP system, a formal 
modification will be required when:
    (1) There is a change of at least 25 percent or $25,000 (whichever 
is greater) in any cost category; or
    (2) There is a change of at least 25 percent or 25 individuals 
(whichever is greater) in the number of individuals to be served in any 
category of program activity.
    (c) The documentation to be submitted to the DINAP Federal 
Representative requesting such a modification shall consist of a letter 
explaining the need for the change and four copies of the proposed 
modification.
    (d) The Grant Officer should notify the Native American grantee of 
tentative approval or disapproval within 10 calendar days of receipt of 
the proposed modifications. The Grant Officer should notify the Native 
American grantee in writing of final approval or disapproval within 30 
calendar days of the receipt of the proposed modification.
    (e) A Native American grantee may make any change in its Program 
Planning Summary and Budget Information Summary without prior approval, 
except as provided in this section.
    (f) Native American grantees shall notify DINAP by submitting a 
modification whenever there is a change in a name, address, or other 
similar information.
    (g) The Department will unilaterally modify a grant when a simple 
funding or performance period increase is required and it is consistent 
with the approved plan.

(Approved by the Office of Management and Budget and assigned OMB 
control number 1205-0213)