Sec. 636.118  Is team switching allowed after contract award?

    Where the offeror's qualifications are a major factor in the 
selection of the successful design-builder, team member switching 
(adding or switching team members) is discouraged after contract award. 
However, the owner may use its discretion in reviewing team changes or 
team enhancement requests on a case-by-case basis. Specific project 
rules related to changes in team members or changes in personnel within 
teams should be explicitly stated by the STD in all project 
solicitations.