[Code of Federal Regulations] [Title 23, Volume 1] [Revised as of April 1, 2003] From the U.S. Government Printing Office via GPO Access [CITE: 23CFR636.201] [Page 204] TITLE 23--HIGHWAYS CHAPTER I--FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION PART 636--DESIGN-BUILD CONTRACTING--Table of Contents Subpart B--Selection Procedures, Award Criteria Sec. 636.201 What selection procedures and award criteria may be used? You should consider using two-phase selection procedures for all design-build projects. However, if you do not believe two-phase selection procedures are appropriate for your project (based on the criteria in Sec. 636.202), you may use a single phase selection procedure or the modified-design-build contracting method. The following procedures are available: ------------------------------------------------------------------------ Criteria for using Selection procedure a selection Award criteria procedure options ------------------------------------------------------------------------ (a) Two-Phase Selection Sec. 636.202..... Lowest price, Procedures (RFQ followed by Adjusted low-bid RFP). (price per quality point), meets criteria/ low bid, weighted criteria process, fixed price/best design, best value. (b) Single Phase (RFP).......... Project not All of the award meeting the criteria in item criteria in Sec. (a) of this 636.202. table. (c) Modified Design-Build (may Any project....... Lowest price be one or two phases). technically acceptable. ------------------------------------------------------------------------