Sec. 636.210  What requirements apply to projects which use the modified design-build procedure?

    (a) Modified design-build selection procedures (lowest price 
technically acceptable source selection process) may be used for any 
project.
    (b) The solicitation must clearly state the following:
    (1) The identification of evaluation factors and significant 
subfactors that establish the requirements of acceptability.
    (2) That award will be made on the basis of the lowest evaluated 
price of proposals meeting or exceeding the acceptability standards for 
non-cost factors.
    (c) The contracting agency may forgo a short listing process and 
advertise for the receipt of proposals from all responsible offerors. 
The contract is then awarded to the lowest responsive bidder.
    (d) Tradeoffs are not permitted, however, you may incorporate cost-
plus-time bidding procedures (A+B bidding), lane rental, or other cost-
based provisions in such contracts.
    (e) Proposals are evaluated for acceptability but not ranked using 
the non-cost/price factors.

[[Page 206]]

    (f) Exchanges may occur (see subpart D of this part).