Sec. 636.305  Can price information be provided to analysts who are reviewing technical proposals?

    Normally, technical and price proposals are reviewed independently 
by separate evaluation teams. However, there may be occasions where the 
same experts needed to review the technical proposals are also needed in 
the review of the price proposals. This may occur where a limited amount 
of technical expertise is available to review proposals. Price 
information may be provided to such technical experts in accordance with 
your procedures.