Sec. 968.422  Progress reports and completion schedule.

    (a) Reports required. Until completion of the activities funded 
under the vacancy reduction program, the grantee shall submit to HUD, in 
a form and at a time prescribed by HUD, the following:
    (1) A report on modernization fund expenditures;
    (2) A narrative report that includes an accounting of the grantee's 
progress against the milestones established in its vacancy reduction 
plan. The report shall include the number of both funded and regular 
turn-over units that have been made ready for occupancy; and
    (3) Any additional information as HUD may require.
    (b) Completion schedule. HUD expects that most work items funded 
under this program will be completed within one year. Work items must be 
completed within two years from the date of funding, or by some other 
time as may be specified in the Notice of Funding Availability, unless 
prior approval is obtained from HUD.

(Approved by the Office of Management and Budget under control number 
2577-0181)