Sec. 32.25  Revision of budget and program plans.

    (a) The budget plan is the financial expression of the project or 
program as approved during the award process. It may include either the 
sum of the Federal and non-Federal shares, or only the Federal share, 
depending upon DoD Component requirements. It shall be related to 
performance for program evaluation purposes whenever appropriate.
    (b) Recipients are required to report deviations from budget and 
program plans, and request prior approvals for budget and program plan 
revisions, in accordance with this section.
    (c) For nonconstruction awards, recipients shall request prior 
approvals from the cognizant grants officer for one or more of the 
following program or budget related reasons.
    (1) Change in the scope or the objective of the project or program 
(even if there is no associated budget revision requiring prior written 
approval).

[[Page 140]]

    (2) Change in a key person specified in the application or award 
document.
    (3) The absence for more than three months, or a 25 percent 
reduction in time devoted to the project, by the approved project 
director or principal investigator.
    (4) The need for additional Federal funding.
    (5) The transfer of amounts budgeted for indirect costs to absorb 
increases in direct costs, or vice versa, if approval is required by the 
DoD Component. DoD Components should require this prior approval only in 
exceptional circumstances. The requirement in each such case must be 
stated in the award document.
    (6) The inclusion, unless waived by the DoD Component, of costs that 
require prior approval in accordance with OMB Circular A-21,\5\ ``Cost 
Principles for Institutions of Higher Education,'' OMB Circular A-
122,\6\ ``Cost Principles for Non-Profit Organizations,'' or Appendix E 
to 45 CFR part 74, ``Principles for Determining Costs Applicable to 
Research and Development under Grants and Contracts with Hospitals,'' or 
48 CFR part 31, ``Contract Cost Principles and Procedures,'' as 
applicable. However, it should be noted that many of the prior approvals 
in these cost principles are appropriately waived only after 
consultation with the cognizant federal agency responsible for 
negotiating the recipient's indirect costs.
---------------------------------------------------------------------------

    \5\ See footnote 1 to Sec. 32.1(a).
    \6\ See footnote 1 to Sec. 32.1(a).
---------------------------------------------------------------------------

    (7) The transfer of funds allotted for training allowances (direct 
payment to trainees) to other categories of expense.
    (8) Unless described in the application and funded in the approved 
awards, the subaward, transfer or contracting out of any work under an 
award. This provision does not apply to the purchase of supplies, 
material, equipment or general support services.
    (9) If required by the DoD Component, the transfer of funds among 
direct cost categories that is described in paragraph (e) of this 
section.
    (d) (1) Except for requirements listed in paragraphs (c)(1) and 
(c)(4) of this section, OMB Circular A-110 authorizes DoD Components, at 
their option, to waive cost-related and administrative prior written 
approvals required by this part and OMB Circulars A-21 and A-122 (but 
see cautionary note at end of paragraph (c)(5) of this section).
    (2) The two prior approvals listed in paragraphs (d)(2)(i) and (ii) 
of this section are automatically waived unless the award document 
states otherwise. DoD Components should override this automatic waiver 
and require the prior approvals, especially for research awards, only in 
exceptional circumstances. Absent an override in the award terms and 
conditions, recipients need not obtain prior approvals before:
    (i) Incurring pre-award costs 90 calendar days prior to award 
(incurring pre-award costs more than 90 calendar days prior to award 
would still require the prior approval of the DoD Component). All pre-
award costs are incurred at the recipient's risk (i.e., the DoD 
Component is under no obligation to reimburse such costs if for any 
reason the recipient does not receive an award or if the award is less 
than anticipated and inadequate to cover such costs).
    (ii) Carrying forward unobligated balances to subsequent funding 
periods.
    (3) Under certain conditions, a DoD Component may authorize a 
recipient to initiate, without prior approval, a one-time, no-cost 
extension (i.e., an extension in the expiration date of an award that 
does not require additional Federal funds) for a period of up to twelve 
months, as long as the no-cost extension does not involve a change in 
the approved objectives or scope of the project. The conditions for 
waiving this prior approval requirement are that the DoD Component must:
    (i) Judge that the recipient's subsequently initiating a one-time, 
no-cost extension would not cause the DoD Component to fail to comply 
with DoD funding policies (for further information on the location of 
DoD funding policies, grants officers may refer to Appendix C to 32 CFR 
part 22).
    (ii) Require a recipient that wishes to initiate a one-time, no-cost 
extension to so notify the office that made the award at least 10 
calendar days before the original expiration date of the award.

[[Page 141]]

    (e) The DoD Component may, at its option, restrict the transfer of 
funds among direct cost categories, functions and activities for awards 
in which the Federal share of the project exceeds $100,000 and the 
cumulative amount of such transfers exceeds or is expected to exceed 10 
percent of the total budget as last approved by the DoD Component. As a 
matter of DoD policy, requiring prior approvals for such transfers 
generally is not appropriate for grants to support research. No DoD 
Component shall permit a transfer that would cause any Federal 
appropriation or part thereof to be used for purposes other than those 
consistent with the original intent of the appropriation.
    (f) For construction awards, recipients shall request prior written 
approval promptly from grants officers for budget revisions whenever:
    (1) The revision results from changes in the scope or the objective 
of the project or program;
    (2) The need arises for additional Federal funds to complete the 
project; or
    (3) A revision is desired which involves specific costs for which 
prior written approval requirements may be imposed consistent with 
applicable OMB cost principles listed in Sec. 32.27.
    (g) When a DoD Component makes an award that provides support for 
both construction and nonconstruction work, the DoD Component may 
require the recipient to request prior approval from the grants officer 
before making any fund or budget transfers between the two types of work 
supported.
    (h) No other prior approval requirements for specific items may be 
imposed unless a deviation has been approved, in accordance with the 
deviation procedures in Sec. 32.4(c).
    (i) For both construction and nonconstruction awards, DoD Components 
shall require recipients to notify the grants officer in writing 
promptly whenever the amount of Federal authorized funds is expected to 
exceed the needs of the recipient for the project period by more than 
$5000 or five percent of the Federal award, whichever is greater. This 
notification shall not be required if an application for additional 
funding is submitted for a continuation award.
    (j) When requesting approval for budget revisions, recipients shall 
use the budget forms that were used in the application unless the grants 
officer indicates a letter of request suffices.
    (k) Within 30 calendar days from the date of receipt of the request 
for budget revisions, the grants officer shall review the request and 
notify the recipient whether the budget revisions have been approved. If 
the revision is still under consideration at the end of 30 calendar 
days, the grants officer shall inform the recipient in writing of the 
date when the recipient may expect the decision.