Sec. 146.10  Notice of new facilities.

    (a) The owner or operator of each OCS facility not in operation 
before April 5, 1982 shall, at least 30 days before the date on-site 
construction of the facility is expected to commence, notify the 
District Commander for the area in which the facility will be located 
of:
    (1) The position in which the facility will be operated;
    (2) The designation assigned to the facility for identification 
under 30 CFR 250.37;
    (3) The date when operation of the facility is expected to commence; 
and
    (4) The date when the facility is expected to be available for 
inspection by the Coast Guard.

[[Page 156]]

    (b) The information required in paragraph (a) of this section may be 
submitted together with an need not repeat information submitted in 
connection with the application and notice requirements in 33 CFR Part 
67 for aids to navigation on the Outer Continental Shelf.