Sec. 148.321  Decision process generally.

    (a) During the 45-day period immediately following the completion of 
the final public hearing on a proposed deepwater port license for a 
designated application area, opportunity is provided for the various 
Federal departments and agencies having expertise concerning, or 
jurisdiction over, any aspect of ownership, construction, or operation 
of deepwater ports or having a duty under the Act with respect thereto 
and the Governor of each adjacent coastal State to formulate and 
transmit to the Secretary their determinations, recommendations, 
opinions and approvals or disapprovals, as the case may be.
    (b) Within 45 days after the expiration of the 45-day period 
described in paragraph (a) of this section, the Secretary approves or 
denies each application for a deepwater port license in the designated 
application area.