Sec. 150.117  Notification to the District Commander.

    (a) At least 30 days before construction of a pipeline, platform, or 
SPM at a deepwater port begins, the licensee shall give notice of 
construction in writing to the District Commander.
    (b) On the date construction of a pipeline, platform or SPM at a 
deepwater port begins, the licensee shall give written notice to the 
District Commander within 24 hours of the lights and fog signals in use 
at the construction site.
    (c) Whenever lights or fog signals are changed during construction 
of a pipeline, platform, or SPM at a deepwater port, the licensee shall 
give written notice of such change to the District Commander within 24 
hours.
    (d) When lights or fog signals used during construction of a 
platform, buoy, or SPM at a deepwater port are replaced with lights or 
fog signals required by Part 149 of this subchapter, the licensee shall 
give written notice of replacement to the District Commander within 24 
hours.
    (e) At least 60 days before the first oil transfer operation begins 
at a deepwater port, the licensee shall give written notice of the 
operation to the District Commander.

[CDG 75-002, 40 FR 52572, Nov. 10, 1975; 40 FR 58143, Dec. 15, 1975]