Sec. 150.129  Response plans.

    (a) The owner or operator of a deepwater port shall prepare and 
submit a response plan meeting the requirements of subpart F of part 154 
for review and approval by the cognizant Captain of the Port (COTP).
    (b) A response plan must be submitted to the cognizant COTP by 
February 18, 1993 or not less than 60 days before the port begins 
operation, which ever is later.

[CGD 91-036, 58 FR 7352, Feb. 5, 1993]