[Code of Federal Regulations]
[Title 33, Volume 2]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 33CFR154.110]

[Page 301]
 
                TITLE 33--NAVIGATION AND NAVIGABLE WATERS
 
   CHAPTER I--COAST GUARD, DEPARTMENT OF HOMELAND SECURITY (CONTINUED)
 
PART 154--FACILITIES TRANSFERRING OIL OR HAZARDOUS MATERIAL IN BULK--Table 
of Contents
 
                           Subpart A--General
 
Sec. 154.110  Letter of intent.

    (a) The facility operator of any facility to which this part applies 
must submit a letter of intent to operate a facility or to conduct 
mobile facility operations to the COTP not less than 60 days before the 
intended operations unless a shorter period is allowed by the COTP. 
Previously submitted letters of intent need not be resubmitted.
    (b) The letter of intent required by paragraph (a) of this section 
may be in any form but must contain:
    (1) The names, addresses, and telephone numbers of the facility 
operator and the facility owner;
    (2) The name, address, and telephone number of the facility or, in 
the case of a mobile facility, the dispatching office; and
    (3) Except for a mobile facility, the geographical location of the 
facility in relation to the associated body of navigable waters.
    (c) The facility operator of any facility for which a letter of 
intent has been submitted, shall within five (5) days advise the COTP in 
writing of any changes of information and shall cancel, in writing, the 
letter for any facility at which transfer operations are no longer 
conducted.

[CGD 75-124, 45 FR 7169, Jan. 31, 1980, as amended by CGD 86-034, 55 FR 
36252, Sept. 4, 1990; CGD 93-056, 61 FR 41458, Aug. 8, 1996]