[Code of Federal Regulations]
[Title 36, Volume 1]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 36CFR14.96]

[Page 227]
 
              TITLE 36--PARKS, FORESTS, AND PUBLIC PROPERTY
 
      CHAPTER I--NATIONAL PARK SERVICE, DEPARTMENT OF THE INTERIOR
 
PART 14--RIGHTS-OF-WAY--Table of Contents
 
                Subpart H--Telephone and Telegraph Lines
 
Sec. 14.96  Procedures.

    Any application under the Act of March 4, 1911, for line right-of-
way in excess of 100 feet in width or for a structure or facility right-
of-way of over 10,000 square feet must state the reasons why the larger 
right-of-way is required. Rights-of-way will not be issued in excess of 
such sizes in the absence of a satisfactory showing of the need 
therefor.

                          Appendix A to Part 14

    Where necessary, these forms should be modified so as to be 
appropriate to the applicant (corporation, association, or individual), 
to the act involved, and to the nature of the project.

                                  Form

    References should be made to the appropriate section of the 
regulations to determine when each of the forms is required.
    Form No. 2 may be signed by any officer or employee of the company 
who is authorized to sign it. However, if it is executed by a person 
other than the President, it must be accompanied by a certified copy of 
the minutes of the Board of Directors meeting or other document 
authorizing such signature unless such certified copy has already been 
filed in the case.
    Forms 1 and 2 to be placed on maps. See Sec. 14.25(a)(7).

                          Engineer's Statement

                                (Form 1)

    ----------(Name of engineer) states he is by occupation a ----------
(Type of engineer) employed by the ----------(Company) to make the 
survey of the ----------(Kind of works) as described and shown on this 
map; that the survey of said works made by him (or under his 
supervision) and under authority, commencing on the ------ day of ------ 
19---- and ending on the ------ day of ------, 19----; and that such 
survey is accurately represented upon this map.
--------------------
Engineer

                         Applicant's Certificate

                                (Form 2)

    This is to certify that ---------- (Engineer), who subscribed the 
statement hereon, is the person employed by the undersigned applicant to 
prepare this map, which has been adopted by the applicant as the 
approximate final location of the works thereby shown, and that this map 
is filed as a part of the complete application, and in order that the 
applicant may obtain the benefits of ----------(Cite statute); and I 
further certify that the right-of-way herein described is desired for
(state purpose)_________________________________________________________
    (Seal)
________________________________________________________________________
Signature of Applicant
________________________________________________________________________
Title
________________________________________________________________________
Company
Attest: