[Code of Federal Regulations]
[Title 38, Volume 2]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 38CFR59.20]

[Page 883]
 
            TITLE 38--PENSIONS, BONUSES, AND VETERANS' RELIEF
 
          CHAPTER I--DEPARTMENT OF VETERANS AFFAIRS (CONTINUED)
 
PART 59--GRANTS TO STATES FOR CONSTRUCTION OR ACQUISITION OF STATE HOMES--
Table of Contents
 
Sec. 59.20  Initial application requirements.

    (a) For a project to be considered for inclusion on the priority 
list in Sec. 59.50 of this part for the next fiscal year, a State must 
submit to VA an original and one copy of a completed VA Form 10-0388 and 
all information, documentation, and other forms specified by VA form 10-
0388 (these forms are set forth at Sec. 59.170 of this part).
    (b) The Secretary, based on the information submitted for a project 
pursuant to paragraph (a) of this section, will approve the project for 
inclusion on the priority list in Sec. 59.50 of this part if the 
submission includes all of the information requested under paragraph (a) 
of this section and if the submission represents a project that, if 
further developed, could meet the requirements for a grant under this 
part.
    (c) The information requested under paragraph (a) of this section 
should be submitted to VA by April 15, and must be received by VA by 
August 15, if the State wishes an application to be included on the 
priority list for the award of grants during the next fiscal year.
    (d) If a State representative believes that VA may not award a grant 
to the State for a grant application during the current fiscal year and 
wants to ensure that VA includes the application on the priority list 
for the next fiscal year, the State representative must, prior to August 
15 of the current fiscal year,
    (1) Request VA to include the application in those recommended to 
the Secretary for inclusion on the priority list, and
    (2) Send any updates to VA.

(Authority: 38 U.S.C. 101, 501, 1710, 1742, 8105, 8131-8137)