[Code of Federal Regulations]
[Title 40, Volume 2]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR51.103]

[Page 145]
 
                   TITLE 40--PROTECTION OF ENVIRONMENT
 
         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
 
PART 51--REQUIREMENTS FOR PREPARATION, ADOPTION, AND SUBMITTAL OF 
IMPLEMENTATION PLANS--Table of Contents
 
                   Subpart F--Procedural Requirements
 
Sec. 51.103  Submission of plans, preliminary review of plans.

    (a) The State makes an official plan submission to EPA only when the 
submission conforms to the requirements of appendix V to this part, and 
the State delivers five copies of the plan to the appropriate Regional 
Office, with a letter giving notice of such action.
    (b) Upon request of a State, the Administrator will provide 
preliminary review of a plan or portion thereof submitted in advance of 
the date such plan is due. Such requests must be made in writing to the 
appropriate Regional Office and must be accompanied by five copies of 
the materials to be reviewed. Requests for preliminary review do not 
relieve a State of the responsibility of adopting and submitting plans 
in accordance with prescribed due dates.

[51 FR 40661, Nov. 7, 1986, as amended at 55 FR 5830, Feb. 16, 1990; 63 
FR 9151, Feb. 24, 1998]