Sec. 55.6  Permit requirements.

    (a) General provisions--(1) Permit applications. (i) The owner or 
operator of an OCS source shall submit to the Administrator or delegated 
agency all information necessary to perform any analysis or make any 
determination required under this section.
    (ii) Any application submitted pursuant to this part by an OCS 
source shall include a description of all the requirements of this part 
and a description of how the source will comply with the applicable 
requirements. For identification purposes only, the application shall 
include a description of those requirements that have been proposed by 
EPA for incorporation into this part and that the applicant believes, 
after diligent research and inquiry, apply to the source.
    (2) Exemptions. (i) When an applicant submits any approval to 
construct or permit to operate application to the Administrator or 
delegated agency it shall include a request for exemption from 
compliance with any pollution control technology requirement that the 
applicant believes is technically infeasible or will cause an 
unreasonable threat to health and safety. The Administrator or delegated 
agency shall act on the request for exemption in accordance with the 
procedures established in Sec. 55.7 of this part.
    (ii) A final permit shall not be issued under this part until a 
final determination is made on any exemption request, including those 
appealed to the Administrator in accordance with Sec. 55.7 of this part.
    (3) Administrative procedures and public participation. The 
Administrator will follow the applicable procedures of 40 CFR part 124 
in processing applications under this part. Until 40 CFR part 124 has 
been modified to specifically reference permits issued under this part, 
the Administrator will follow the procedures in part 124 used to issue 
Prevention of Significant Deterioration (``PSD'') permits.
    (4) Source obligation. (i) Any owner or operator who constructs or 
operates an OCS source not in accordance with the application submitted 
pursuant to this part 55, or with any approval to construct or permit to 
operate, or any owner or operator of a source subject to the 
requirements of this part who commences construction after the effective 
date of this part without applying for and receiving approval under this 
part, shall be in violation of this part.
    (ii) Any owner or operator of a new OCS source who commenced 
construction prior to the promulgation date of this rule shall comply 
with the requirements of paragraph (e) of this section.
    (iii) Receipt of an approval to construct or a permit to operate 
from the Administrator or delegated agency shall not relieve any owner 
or operator of the responsibility to comply fully with the applicable 
provisions of any other requirements under Federal law.
    (iv) The owner or operator of an OCS source to whom the approval to 
construct or permit to operate is issued under this part shall notify 
all other owners and operators, contractors, and the subsequent owners 
and operators associated with emissions from the source, of the 
conditions of the permit issued under this part.
    (5) Delegation of authority. If the Administrator delegates any of 
the authority to implement and enforce the requirements of this section, 
the following provisions shall apply:
    (i) The applicant shall send a copy of any permit application 
required by this section to the Administrator through the EPA Regional 
Office at the same time as the application is submitted to the delegated 
agency.
    (ii) The delegated agency shall send a copy of any public comment 
notice required under this section or Secs. 55.13 or 55.14 to the 
Administrator through the EPA Regional Office.
    (iii) The delegated agency shall send a copy of any preliminary 
determination and final permit action required under this section or 
Secs. 55.13 or 55.14 to the Administrator through the EPA Regional 
Office at the time of the determination and shall make available to the 
Administrator any materials used in making the determination.
    (b) Preconstruction requirements for OCS sources located within 25 
miles of States' seaward boundaries. (1) No OCS source to which the 
requirements of Secs. 55.13 or 55.14 of this part apply shall

[[Page 110]]

begin actual construction after the effective date of this part without 
a permit that requires the OCS source to meet those requirements.
    (2) Any permit application required under this part shall not be 
submitted until the Administrator has determined whether a consistency 
update is necessary, pursuant to Sec. 55.12 of this part, and, if the 
Administrator finds an update to be necessary, has published a proposed 
consistency update.
    (3) The applicant may be required to obtain more than one 
preconstruction permit, if necessitated by partial delegation of this 
part or by the requirements of this section and Secs. 55.13 and 55.14 of 
this part.
    (4) An approval to construct shall become invalid if construction is 
not commenced within 18 months after receipt of such approval, if 
construction is discontinued for a period of 18 months or more, or if 
construction is not completed within a reasonable time. The 18-month 
period may be extended upon a showing satisfactory to the Administrator 
or the delegated agency that an extension is justified. Sources 
obtaining extensions are subject to all new or interim requirements and 
a reassessment of the applicable control technology when the extension 
is granted. This requirement shall not supersede a more stringent 
requirement under Secs. 55.13 or 55.14 of this part.
    (5) Any preconstruction permit issued to a new OCS source or 
modification shall remain in effect until it expires under paragraph 
(b)(4) of this section or is rescinded under the applicable requirements 
incorporated in Secs. 55.13 and 55.14 of this part.
    (6) Whenever any proposed OCS source or modification to an existing 
OCS source is subject to action by a Federal agency that might 
necessitate preparation of an environmental impact statement pursuant to 
the National Environmental Policy Act (42 U.S.C. 4321), review by the 
Administrator conducted pursuant to this section shall be coordinated 
with the environmental reviews under that Act to the extent feasible and 
reasonable.
    (7) The Administrator or delegated agency and the applicant shall 
provide written notice of any permit application from a source, the 
emissions from which may affect a Class I area, to the Federal Land 
Manager charged with direct responsibility for management of any lands 
within the Class I area. Such notification shall include a copy of all 
information contained in the permit application and shall be given 
within 30 days of receipt of the application and at least 60 days prior 
to any public hearing on the preconstruction permit.
    (8) Modification of existing sources. The preconstruction 
requirements above shall not apply to a particular modification, as 
defined in Sec. 55.13 or Sec. 55.14 of this part, of an existing OCS 
source if:
    (i) The modification is necessary to comply with this part, and no 
other physical change or change in the method of operation is made in 
conjunction with the modification;
    (ii) The modification is made within 24 months of promulgation of 
this part; and
    (iii) The modification does not result in an increase, in excess of 
any de minimus levels contained in the applicable requirements of 
Secs. 55.13 and 55.14, of potential emissions or actual hourly emissions 
of a pollutant regulated under the Act.
    (9) Compliance plans. Sources intending to perform modifications 
that meet all of the criteria of paragraph (b)(8) of this section shall 
submit a compliance plan to the Administrator or delegated agency prior 
to performing the modification. The compliance shall describe the 
schedule and method the source will use to comply with the applicable 
OCS requirements within 24 months of the promulgation date of this part 
and shall include a request for any exemptions from compliance with a 
pollution control technology requirement that the applicant believes is 
technically infeasible or will cause an unreasonable threat to health 
and safety. The Administrator or delegated agency shall act on the 
request for exemption in accordance with the procedures established in 
Sec. 55.7 of this part.
    (i) The Administrator or delegated agency shall review the 
compliance plan and provide written comments to the source within 45 
days of receipt of such plan. The source shall provide a written 
response to such comments as required by the reviewing agency.

[[Page 111]]

    (ii) Receipt and review of a compliance plan by the Administrator or 
delegated agency shall not relieve any owner or operator of an existing 
OCS source of the responsibility to comply fully with the applicable 
requirements of Secs. 55.13 and 55.14 of this part within 24 months of 
promulgation of this part.
    (c) Operating permit requirements for sources located within 25 
miles of States' seaward boundaries. (1) All applicable operating permit 
requirements listed in this section and incorporated into Secs. 55.13 
and 55.14 of this part shall apply to OCS sources.
    (2) The Administrator or delegated agency shall not issue a permit 
to operate to any existing OCS source that has not demonstrated 
compliance with all the applicable requirements of this part.
    (3) If the COA does not have an operating permits program approved 
pursuant to 40 CFR part 70 or if EPA has determined that the COA is not 
adequately implementing an approved program, the applicable requirements 
of 40 CFR part 71, the Federal operating permits program, shall apply to 
the OCS sources. The applicable requirements of 40 CFR part 71 will be 
implemented and enforced by the Administrator. The Administrator may 
delegate the authority to implement and enforce all or part of a Federal 
operating permits program to a State pursuant to Sec. 55.11 of this 
part.
    (d) Permit requirements for sources located beyond 25 miles of 
States' seaward boundaries. (1) OCS sources located beyond 25 miles of 
States' seaward boundaries shall be subject to the permitting 
requirements set forth in this section and Sec. 55.13 of this part.
    (2) The Administrator or delegated agency shall not issue a permit-
to-operate to any existing OCS source that has not demonstrated 
compliance with all the applicable requirements of this part.
    (e) Permit requirements for new sources that commenced construction 
prior to September 4, 1992--(1) Applicability. Sec. 55.6(e) applies to a 
new OCS source, as defined by section 328 of the Act, that commenced 
construction before September 4, 1992.
    (2) A source subject to Sec. 55.6(e) shall comply with the following 
requirements:
    (i) By October 5, 1992, the owner or operator of the source shall 
submit a transitional permit application (``TPA'') to the Administrator 
or the delegated agency. The TPA shall include the following:
    (A) The information specified in Secs. 55.4(b)(1) through 
Sec. 55.4(b)(9) of this part;
    (B) A list of all requirements applicable to the source under this 
part;
    (C) A request for exemption from compliance with any control 
technology requirement that the applicant believes is technically 
infeasible or will cause an unreasonable threat to health and safety;
    (D) An air quality screening analysis demonstrating whether the 
source has or is expected in the future to cause or contribute to a 
violation of any applicable State or Federal ambient air quality 
standard or exceed any applicable increment. If no air quality analysis 
is required by the applicable requirements of Secs. 55.13 and 55.14, 
this requirement does not apply;
    (E) Documentation that source emissions are currently being offset, 
or will be offset if the source has not commenced operation, at the 
ratio required under this part, and documentation that those offsets 
meet or will meet the requirements of this part; and
    (F) A description of how the source is complying with the applicable 
requirements of Secs. 55.13 and 55.14 of this part, including emission 
levels and corresponding control measures, including Best Available 
Control Technology (``BACT'') or Lowest Achievable Emission Rates 
(``LAER''), but excluding the requirements to have valid permits.
    (ii) The source shall expeditiously complete its permit application 
in compliance with the schedule determined by the Administrator or 
delegated agency.
    (iii) The source shall comply with all applicable requirements of 
this part except for the requirements of paragraph (a)(4)(i) of this 
section. The source shall comply with the control technology 
requirements (such as BACT or LAER) set forth in the TPA that would

[[Page 112]]

be applicable if the source had a valid permit.
    (iv) Any owner or operator subject to this subsection who continues 
to construct or operate an OCS source thirty days from promulgation of 
this part without submitting a TPA, or continues to construct or operate 
an OCS source not in accordance with the TPA submitted pursuant to 
paragraph (e) of this section, or constructs or operates an OCS source 
not in accordance with the schedule determined by the permitting 
authority, shall be in violation of this part.
    (3) Upon the submittal of a permit application deemed to be complete 
by the permitting authority, the owner or operator of the source shall 
be subject to the permitting requirements of Secs. 55.13 and 55.14 of 
this part that apply subsequent to the submission of a complete permit 
application. When a source receives the permit or permits required under 
this part, its TPA shall expire.
    (4) Until the date that a source subject to this subsection receives 
the permit or permits required under this part, that source shall cease 
operation if, based on projected or actual emissions, the permitting 
authority determines that the source is currently or may in the future 
cause or contribute to a violation of a State or Federal ambient air 
quality standard or exceed any applicable increment.

[57 FR 40806, Sept. 4, 1992, as amended at 61 FR 34228, July 1, 1996; 62 