Sec. 57.405  Formulation, approval, and implementation of requirements.

    (a) SCS content of the application. The requirements of 
Sec. 57.203(d) shall be satisfied with respect to this subpart as 
follows:
    (1) Each NSO application shall include a complete description of any 
supplementary control system in operation at the smelter at the time of 
application and a copy of any SCS operational manual in use with that 
system.
    (2) Each NSO application shall contain proposed NSO provisions for 
compliance with the requirements of Secs. 57.401, 57.402 (c), (d), and 
(f), 57.403, 57.404, and 57.405 (b)(2).
    (3) Each NSO application shall include a specific plan for the 
development of a system fulfilling the requirements of Sec. 57.402(a), 
(b), and (e) (covering air quality monitoring network, meteorological 
network, and the SCS operational manual).
    (b) SCS content of the order. (1) Each NSO shall include an approved 
version of the plan described in paragraph (a)(3) of this section and 
shall provide increments of progress towards its completion. Each NSO 
shall require, upon completion of the measures specified in the approved 
plan, submission of a report which describes each element of the SCS and 
explains why the elements satisfy the requirements of the plan and 
submission of a copy of the SCS operational manual developed under the 
plan.
    (2) Each NSO shall require the submission of a final report, within 
6 months of the required date for completion of the measures specified 
in the approved plan evaluating the performance and adequacy of the SCS 
developed pursuant to the approved plan. The report shall include:
    (i) A detailed description of how the criteria that form the basis 
for particular curtailment decisions were derived;
    (ii) A complete description of each SCS element listed in 
Sec. 57.402 (a)

[[Page 148]]

through (d) (covering monitoring, meteorology, and the DLA), and an 
explanation of why the elements fulfill the requirements of those 
sections;
    (iii) A reliability study demonstrating that the SCS will prevent 
violations of the NAAQS in the smelter's DLA at all times. The 
reliability study shall include a comprehensive analysis of the system's 
operation during one or more three-month seasonal periods when 
meteorological conditions creating the most serious risk of NAAQS 
violations are likely to occur. Where it is impossible, because of time 
restraints, to include in such a study and analysis of the three month 
seasonal period with meteorological conditions creating the most serious 
risk of NAAQS violations, the study shall analyze the system's operation 
on the basis of all available information. The NSO shall provide that in 
such case, a supplemental reliability study shall be submitted after the 
end of the worst case three-month period as a part of the next semi-
annual report required under Sec. 57.402(f).
    (iv) A copy of the current SCS operational manual.
    (c) Amendment of the NSO. Each NSO shall be amended, if necessary, 
within 3 months of completion of the measures required under the SCS 
development plan and also, if necessary, within three months of 
submission of the final report or any supplement to the final report 
required under paragraph (b)(2) of this section, to reflect the most 
current approved elements of the SCS and, as appropriate, to fulfill all 
other requirements of this subpart. Each NSO shall also be subsequently 
amended (as provided in Sec. 57.104) whenever necessary as a result of 
the program required by Sec. 57.402(f) or to reflect improved SCS 
operating procedures or other system requirements.