[Code of Federal Regulations]
[Title 40, Volume 5]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR57.701]

[Page 151]
 
                   TITLE 40--PROTECTION OF ENVIRONMENT
 
         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
 
PART 57--PRIMARY NONFERROUS SMELTER ORDERS--Table of Contents
 
               Subpart G--Compliance Schedule Requirements
 
Sec. 57.701  General requirements.


    This section applies to all smelters applying for an NSO. Each NSO 
shall require the smelter owner to meet all of the requirements within 
the NSO as expeditiously as practicable but in no case later than the 
deadlines contained in this subpart or any other section of these 
regulations. For requirements not immediately effective, the NSO shall 
provide increments of progress and a schedule for compliance. Each 
schedule must reflect the extent to which any required equipment or 
systems are already in place and the extent to which any required 
reports or studies have already been completed. Requirements for 
smelters to submit compliance schedules and the procedures which they 
must follow are outlined below.