[Code of Federal Regulations]
[Title 40, Volume 5]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR57.705]
[Page 153]
TITLE 40--PROTECTION OF ENVIRONMENT
CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
PART 57--PRIMARY NONFERROUS SMELTER ORDERS--Table of Contents
Subpart G--Compliance Schedule Requirements
Sec. 57.705 Contents of SIP Compliance Schedule required by Sec. 57.201(d)
(2) and (3).
This section applies to smelters which are required to submit a SIP
Compliance Schedule as discussed below.
(a) Each SIP Compliance Schedule required by Sec. 57.201(d) (2) and
(3) must contain the following elements:
(1) Description of the overall design of the SO2 control
system(s) to be installed;
(2) Descriptions of specific process hardware to be used in
achieving compliance with the SIP emission limitation including gas
capacity values;
(3) The date by which contracts will be let or purchase orders
issued to accomplish any necessary performance improvements;
(4) The date for initiating on-site construction or installation of
necessary equipment;
(5) The date by which on-site construction or installation of
equipment is to be completed;
(6) The date for achievement of final compliance with SIP emission
limitations; and
(7) Any other measures necessary to assure compliance with all SIP
requirements as expeditiously as practicable.
(b) Operations of SCS. Smelters to which Sec. 57.705 is applicable
must comply with all elements of Sec. 57.703.